MQXBP1: Meeting on anti-cryostat 10/03/2020
Anti-cryostat court
- Inserted
- Nothing else to be done, just the test of CFD, vacuum + cool down, to verify everything is well installed. Will be done this week.
Anti-cryostat long:
- Inserted
- There is one temperature sensors broken (2nd, it is the one closer to the bellows, outside the cold mass. There are 7 in the long, 2nd in the sort). It is not critical, we will work without it.
General aspects:
- The control is done with the sensors that are inside the cold mass. Regulation is done with the average, but a maximum and minimum can be set. The PID heats based on the average, it is just on/off. The main concern is if there not enough power. The resistance of the real object is the same as the computed, and the power delivered is also as computed, the question is now if the computed nominal power is enough to keep the anti-cryostat cold. The maximum current is 1 A, 28 V.
- We need a check on the N2 flow needed in case we need to cool down. The aim is to have sufficient flow, SM18 to provide the flow to Vittorio.
- Possible issues:
- Not enough power to heat. Plan B is to bricole something and go to manual. Or make the vacuum and close, keep testing the magnet anyway. We need to order the brides. One is available, the other one needs to be ordered. Tukka to launch production of a second M40 bride, there is already one done (Pierre Moyret).
- Insulation test of the anti-cryostat is done before connecting control system. The test is done at 100 V, the control is giving less than 50 V, so should be ok.
Next steps:
- Next week the magnet will be moved to SM18. This week there is still mechanical work to be done in SMA18.
- The mounting between short and long is done by sm18 people next week. There is an helicoflex join (SM18 and Vittorio think is ok, and anyway this is something that is checked before launching the cool down).