CWDM SM-VTRx project update meeting

→ Europe/Zurich
CERN

CERN

Subsequent discussions on NanoFIP with BE-CO

  • NanoFIP is a WorldFIP Agent (slave) in the form of a rad-tol FPGA-based FMC 
    • https://www.ohwr.org/project/nanofip
    • https://forums.ohwr.org/c/fmc-nanofip
    • Developed and supported by BE-CO
    • Compatible with the current WorldFIP infrastructure in the LHC (e.g. masters, cables, 31.25kbps)
      • It will be able to operate at higher data rates with updated masters (up to and 2.5Mbps)
    • It features a subset of the WorldFIP services
    • It requires a carrier board
      • CO offers an FPGA-based FMC carrier in compact PCI form-factor
      • Custom carrier boards may be used
    • It features 16 Inputs and 16 outputs for slow control
    • New revision of the NanoFIP FMC foreseen
      • Ruggedized version following BI-BL specifications
      • Added I2C/SPI slave mode capability (NanoFIP will be the slave)
      • New hardware features may be added by CO if required (and possible)
    • Its FPGA is used at 50%, so It is possible to add application specific features
      • Most of other teams at CERN using NanoFIP add application specific features
        • CO only supports the base functionality
    • The NanoFIP FPGA gateware may be used as IP Core on other FPGAs
    • Low cost: < 200CHF
  • NanoFIP for slow control of BPM LHC consolidation:
    • WoldFIP infrastructure already available
    • For BPM we may fabricate our own simplified rad-tol FMC carrier with no FPGA (we already have one on the NanoFIP)
    • A single NanoFIP per crate would be sufficient
    • We can add an I2C master for programming the CWDM-VTRx
      • It would use the already existing I/Os for slow control
  • Further discussion required between BP and BL since both BPM LHC Consolidation and BLM LHC may use NanoFIP and share the crate in LHC
There are minutes attached to this event. Show them.
    • 10:00 → 10:20
      Latest CWDM SM-VTRx Characterisation Status 20m
      Speakers: Carmelo Scarcella (CERN), Manoel Barros Marin (CERN)

      Latest CWDM SM-VTRx Characterisation Status (Carmello)

      16 CWDM Single-Mode Versatile Link modules in new SFP enclosure now available (4 per laser wavelength)

      All 16 successfully tested for operation as:

      • Transmitter @ 5.12Gb/s
        • Using default bias, modulation and rise/fall emphasis
        • Average laser power >2.5mA
      • Transmitter @ 5.12Gb/s with lpGBT pre-emphasis for input signals
        • Using optimised bias, modulation and rise/fall emphasis
        • Better eye-diagram with reduced power ~1.5mA
      • Transmitter @ 10.24Gb/s with lpGBT pre-emphasis for input signals
        • Nice eye diagram maintained with average power ~1.5mA
      • Receiver @ 5.12Gb/s
        • Bit error rate shows good uniformity for all 16 modules

       Discussion:

      • Long-term reliability
        • Prediction important
        • Expected to be similar to existing VTRx as only component which is different is the laser die
        • However working in different configuration of laser driver
        • Estimate based on component information (MIL)  (ACTION: EP)
      • Pre-emphasis of input when not using lpGBTx
        • Need to ensure this is still OK by systems not intending to use lpGBTx
        • (ACTION: BI-BP to check this for direct ADC solution)
      • SFP compatibility
        • Standard pin-out used BUT
          • Commercial SFPs use 3.3V while VTRx uses 2.5V
            • Need to ensure this is correct on power-up
          • Rx & Tx pins correctly routed but P/N inversion compared to SFP standard
        • Component tolerances
          • What is expected? In particular for output power.
          • Can this cause saturation in standard SFP receivers?
          • Should be able to see if this is an issue from data sheets of commonly used receivers
            • Should not forget attenuation in fibre & fibre connections for real installations
          • ACTION: BI to provide EP with such data sheets to see if this is an issue
      • Request for documentation (ACTION: EP to provide latest layout, schematics as well as general VTRx documentation & application notes)

       Other follow-up ACTIONS:

      • Possible optimisation for BPM project where receiver is not required
        • 2 options
          • Not to populate receiver
          • 2 in one design for transmitter
        • Needs careful evaluation for Cost saving v overheads
          • Overheads
            • 2 designs
            • 2 qualifications
            • No common building blocks for future designs
            • No general standard pool of spares
            • No way back for BPM system if receiver later required
        •  ACTION: EP to provide BI with estimated cost saving for final decision
      • Setting-up default VTRx values
        • Request to modify defaults by BI-BP
          • Requires ASIC re-design
            • EP comments that manpower not available
            • Also requires production of new masks with significant additional cost
          • May not be optimal for users not requiring 10Gb/s transmission
          • DECISION: Not to pursue this approach
        • Can be set by lpGBTx
          • LpGBT order deadline by Summer 2020 (ACTION: Manoel to contact EP for deadline extension or future batch productions)
          • If lpGBTx not used then need to foresee I2C bus
            • Can this be provided by nanoFIP?
            • Investigate possible input to new nanoFIP design (ACTION: Eva & Manoel to contact BE-CO)
      • Number of units
        • Currently estimating a total of ~8000
          • ~5000 for BPM
          • ~3000 for BLM

       BI specific follow-up:

      • Need to coordinate future developments with this component
        • Set-up design kit for all future designs
        • Should we coordinate this through a new BI rad-hard link forum (include Leonardo - EP - in any discussions)?
      • BI-BP to study best layout for the front-end board to set-up VTRx
        • Use of additional receiver & fibre v NanoFIP or FPGA solution
      • ASIC development
        • Look at ultimate limit of VTRx in final radiation environment
          • Likely to be a fluence not TID issue
          • BI to provide input to EP on composition & energy of expected fluence at representative locations to get a better estimation on the final radiation tolerance
    • 10:20 → 10:40
      Future projects for CWDM SM-VTRx in the BI-BP Section 20m
      Speaker: Manoel Barros Marin (CERN)
    • 10:40 → 11:00
      Future projects for CWDM SM-VTRx in the BI-BL Section 20m
      Speakers: Francesco Martina (University of Liverpool (GB)), Manoel Barros Marin (CERN)