MQXFBP2:
- Coils will be finished CW20-21
- The plan is to instrument coils CW24-26. We will profit to define the path of the fibers such that we don't have issues later on with the rotation tool.
- Activities on MQXFBMT2 will continue from CW21. Mechanical lab will provide support optimizing resources (many things can be done remotely. 1.5 FTE from May 11th, but to work on LS2 activities, 2-3 FTE from May 18th)
- Rods SG will be routed to the magnet non-connection side through the yoke alignment features. Fiber optics are already in the 'good' side. How the cables are fixed will be defined once we are back with the real object in front of us.
MQXFS7:
- Coils will be instrumented with electrical SG + Fiber Optics
- Not clear yet when the assembly will be done (one of the coils needs still to be impregnated, and we need the structure from MQXFS6c, still to be tested). Tentative July-September