GIF++ installation and schedule meeting
Vidyo ONLY
CERN
-
-
09:20
→
09:40
Plans for restart of the facility & CoVid Precautions 20m
WILL BE UPDATED DURING THE MEETING !!!
CoVid-19 Risk Assessment for the Facility : https://edms.cern.ch/document/2376286/1
General guideline :
- ONE setup to enter the bunker at any given time.
- All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
- Traceability of people on site : Logbook ! - List all the people you encountered.
- General access Wednesday is suspended for the time being
Presence at GIF needs to be limited to minimum. If you can work from remote - please do.
If your IMPACT has not been resumed - please do not come to the GIF.
(for exceptions, please contact Giuseppe or Martin)Restart of facility so far :
- Week 21 : First restart. ATLAS -sTGC
- Week 22 : ATLAS MM
- Week 23 : CMS -CSC
As for the next few weeks, Irradiation request have to be submitted via the TC or Group Leader to the "EP Ramp-Up Coordinator" for approval.
We hope to be in a more relaxed situation in mid-June / July
----------------------------------
ATLAS-MM : (Alain)ATLAS - sTGC :
CMS-CSC:
EP-DT1:
EP-DT2 :
CMS-DT:
EcoGas :
CMS-RPC :
Cosmic (scintillators) Trolley :ATLAS-RPC:
==========================================================Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
-
09:40
→
09:45
Long Term Planing - General Items 5m
Discussion : Muon Beam intensity
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
-
09:45
→
09:50
New requests for tests at GIF 5m
introduction, goal of the test, plan, needs
BLM measuring campaign announced / ≈ 100 BLM, 2 days approx.
Dates to be confirmed soon.Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
MPI Munich would like to perform ageing tests of sMDT chambers in the GIF++ starting from about June this year.
Lab on Fiber (LOF) dosimeter
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF) -
09:50
→
09:55
Announcements 5m
-
IMPACTS for 2020 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-
09:50
→
09:55
Infrastructure & Upgrades to the Facility 5m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)-
Cosmic Trigger 10m
-
09:20
→
09:40