    • 09:20 → 09:40
      Plans for restart of the facility & CoVid Precautions 20m

      WILL BE UPDATED DURING THE MEETING !!!

      CoVid-19 Risk Assessment for the Facility :  https://edms.cern.ch/document/2376286/1

      General guideline :

      • ONE setup to enter the bunker at any given time.
      • All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
      • Traceability of people on site :  Logbook ! - List all the people you encountered.
      • General access Wednesday is suspended for the time being

      Presence at GIF needs to be limited to minimum. If you can work from remote - please do.

      If your IMPACT has not been resumed - please do not come to the GIF.
      (for exceptions, please contact Giuseppe or Martin)

      Restart of facility so far :

      • Week 21 : First restart.  ATLAS -sTGC
      • Week 22 : ATLAS MM
      • Week 23 : CMS -CSC
      • Week 24 :

      As for the next few weeks, Irradiation request have to be submitted via the TC or Group Leader to the "EP Ramp-Up Coordinator" for approval.

      We hope to be in a more relaxed situation in mid-June / July

       

      ----------------------------------

      ATLAS-MM :  (Alain) 

      ATLAS - sTGC :  one test this week, another test tomorrow morning. Next Tue morning. 

      CMS-CSC:  replace of electronic parts - 2h foreseen on Wednesday, several hours of source OFF needed.

      EP-DT1:   He line installed in gas room last week.

      EP-DT2 :  Access request next week - 1h

      CMS-DT:  Expected to return to bunker around September.

      EcoGas : checking chambers from next week

      CMS-RPC :  Start prob. next week.

      Cosmic (scintillators) Trolley :

      ATLAS-RPC: expected news next week.
      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe 

      UPSTREAM : Default filter settings :  2.2 

      DOWNSTREAM :  Default filter settings :  1

      -------------------------------------------------------------------------------------------------------

    • 09:40 → 09:45
      Long Term Planing - General Items 5m

      Current estimated NA beam start : 12/07/2021  (2.5 months delayed)

       

      Discussion : Muon Beam intensity

       

      ---------------------------------------------------------

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.
       

    • 09:45 → 09:50
      New requests for tests at GIF 5m

      introduction, goal of the test, plan, needs

      MPI Munich would like to perform ageing tests of sMDT chambers in the GIF++ starting from about October 2020 to December 2021.
       
      BLM measuring campaign announced / ≈ 100 BLM, 2 days approx. 
      Dates to be confirmed soon.

      Bulgaria academy of science -> testing of new type of radiation monitor system

      A new setup of ALICE-RPC will come. More news in coming weeks.

      Lab on Fiber (LOF) dosimeter

      Gas recuperation system to be installed - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.
      (DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)

    • 09:50 → 09:55
      Announcements 5m
      • IMPACTS for 2020 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

      • New Announcements 5m
      • AOB 5m
    • 09:50 → 09:55
      Infrastructure & Upgrades to the Facility 5m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Improvements to the gas monitoring (incoming / primary) needed ?

       

      EHN1 AUG Test scheduled for beginning of April. - POSTPONED to JUNE/JULY

      Need to install a gas patch panel in the upstream area. To be scheduled.

      • LS2 restrictions & interventions 5m

        Ongoing :
        =============

         

        • Chilled water : Interruption until end of June.

        •  
      • Cosmic Trigger 10m