From B. Panev 15 July 2020
The EE team is in status waiting for WCC to be oriented.
As you know, the good news is that there is an agreement with EN-EL (FLOE) for WCC.
The completion of the remaining activities after orientation will take several days.
Remaining activities:
1. Connection of the WCC - MPE
2. Pressure tests and switch-on the water circulation - MSC and MPE 3. Snubber capacitor installation - MPE 4. Connection of the resistors - MPE 5. Closing the switch compartments - MPE 6. Commissioning with current prior going in operation