Presents:
CERN: Roberta, Pedro
CNR: Lino
UoA: Vangelis
4DSoft: Istvan, Andor
Absent: ENG
INTEGRATION ACTIVITY (CERN)
- first deployment test executed for IB 0.4.0
- 22 open bugs
- short delay cumulated on this activity (deadline was end of November) should be recovered during next week, this does not cause any delay for the testing activity
- 3 open issues are being discussed in parallel between CERN, ENG, CNR (update on this on twiki)
- Savane reflects information about deployment test IB 0.3.0: 44 services currently integrated and ready for testing activity
ACTION: continue discussion on open issues off-line
TESTING ACTIVITY (4DSOFT)
- information needed received from partners
- strategy: start from tests that do not require gLite infrastructure while finalising configuration of gLite
- bugs will be submitted to savane, no web interface to show the results of the tests
- deadline for finalising the testing activity still confirmed for the end of December
ACTION: start testing services not using g-Lite, submit bugs to savane
Agreement to increase the frequency of the meetings to twice a week (Wed-Fri at 10h)
ACTION: CERN set up the next confcall
DISCUSSION ON INTEGRATION OPEN ISSUES
Being updated on:
https://twiki.cern.ch/twiki/bin/view/DILIGENT/DiligentIntegrationIssues