Notes on the instrumentation:
- TT822 was disconnected after the repair of the capillary (between CD1 and CD2)
- We connected the main busbars to measure coil & splice resistance during CD/WU. We haven't connected the correctors, TBD if necessary (1/2 day work)
Notes on the test program:
- Phase 1: standard procedure, no comments
- Phase 2:
- Add an additional step between 150 and 80 K to avoid such large delta-T
- 30 g/s may be difficult to achieve.
- Phase 3: after the data analysis, we do this CD/WU to validate the new parameters for the next MBH magnets. This needs to be done before the CD of MBHB-003 (S4)