GIF++ installation and schedule meeting
Vidyo ONLY
CERN
-
-
09:20
→
09:40
Weekly planning 20m
WILL BE UPDATED DURING THE MEETING !!!
CoVid-19 Risk Assessment for the Facility : https://edms.cern.ch/document/2376286/1
General guideline :
- ONE setup to enter the bunker at any given time.
- All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
- Traceability of people on site : Logbook ! - List all the people you encountered.
- General access Wednesday is suspended for the time being
Presence at GIF needs to be limited to minimum. If you can work from remote - please do.
If your IMPACT has not been resumed - please do not come to the GIF.
(for exceptions, please contact Giuseppe or Martin)----------------------------------
Electronic locks now activated in the preparation area + service area !
(please subscribe to "GIF-ServiceArea" e-group)EN-EL Intervention : 1 week full power cut 21-25 September
ACCESS to EHN1 - FORBIDDEN for the duration of the interventionAUG Test EHN1 : 5-7 Oct. (3 days) (maybe we can shorten the 3 days)
Next weekly meeting : Wednesday 9h15
----------------------------------
ATLAS-MM : Two new detectors in bunker now - for one week.
SM1 long term chamber inside bunker (2-3 months). Iso-butan test ongoing.
Monday access to remove detectors, Wednesday new detectors will be installed.
ATLAS - sTGC : Several chambers arrived, 2 chamber in bunker under test.
some problematic chambers in preparation area.
CMS-CSC: Plan of restarting next week. Preparations. Irradiation to start after EN-EL intervention.
EP-DT1: Measurements campaign is over and the setup is moved out (placed near the wall, Saleve side).
EP-DT2 : New detector installed last week in the EP-DT2 trolley. The aging test with eco-friendly gas mixture are going well.
CMS-DT: Expected to return to bunker around September.
EcoGas : Next week a new detector will be installed. After that the test campaign will be resumed using standard mixture (R134a, iso-butane, and SF6)
CMS-RPC : (no report) iRPC trolley removed. In preparation area. To be moved next Wednesday.
Radiation program resumed.
Trolley 147914 goes out next week.Cosmic (scintillators) Trolley :ATLAS-RPC: Coming back end of September. Ageing test of modules. Might need to go in the upstream field.
We will discuss in start of September.
ATLAS-sMDT : Installation of gas pipes (small cable tray) first week of September (02.09)
New plan : upstream 2 meter. Arriving last week of September.
==========================================================Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1--------------------------------------------------------------------------------------------------
-
09:40
→
09:45
Long Term Planing - General Items 5m
Upgrade WinCCOA of our dataserver: POSTPONED
02.09.2020 all morning - postponed due to some issue. Sylvain will tell us when it will be next available slot.Current estimated NA beam start : 12/07/2021 (2.5 months delayed)
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
- https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
- https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N
-
09:45
→
09:50
New requests for tests at GIF 5m
introduction, goal of the test, plan, needs
MPI Munich would like to perform ageing tests of sMDT chambers in the GIF++ starting from about October 2020 to December 2021.BLM measuring campaign announced / ≈ 100 BLM, 2 days approx.
Dates to be confirmed soon.Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
Lab on Fiber (LOF) dosimeter
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF) -
09:50
→
09:55
Announcements 5m
-
IMPACTS for 2020 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-
09:50
→
09:55
Infrastructure & Upgrades to the Facility 5m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)-
Cosmic Trigger 10m
-
09:20
→
09:40