HL-LHC BPM Design

→ Europe/Zurich
Dmitry Gudkov (Budker Institute of Nuclear Physics (RU)), Emilien Rigutto (CERN), Gerhard Schneider (CERN), Michal Krupa (CERN), Nicolas Sebastien Chritin (CERN)

1. Bracket modification suggested - open holes OK, small changed confirmed, the integration to be checked with Fabrice

  • springs --> to be confirmed after quench force check: action Dmitry

2. Welding machines: ok, model confirmed, can be integrated

Cutting machines: no final machine design exists yet, no integration is possible for the moment

Welding and cutting machines drawings should be discussed with VSC (who does them), Nicolas will discuss with Fabrice about possible plans for welding and cutting operations drawings

3. Electrodes design: simulation is underway, meeting with Karol next week.

4. D2 to be modified to have more room for cables --> action Nicolas

5. 16.11. --> drawings to be released for final design review

There are minutes attached to this event. Show them.
    • 15:30 → 15:40
      Design of covers and springs for type B BPM 10m
    • 15:40 → 15:50
      Integration of BPMs and welding machines representation on the drawings 10m
    • 15:50 → 16:00
      Electrodes Design 10m
    • 16:00 → 16:05
      D2 body update 5m
    • 16:05 → 16:15
      Plans for drawings' release 10m
    • 16:15 → 16:25
      AOB 10m