  • See Putting EOSCTALHCB into Production (CodiMD)
  • Successful 200TB test with 10 tape drives and one buffer server for 2.5GB/s of constant archival throughput. Chris will now recall the files.

TO DO/Schedule

  • TPC test from EOS LHCb to T1s
  • DAQ test should be possible in November (tentatively 9 Nov 2020)