HL-LHC BPM Design
Design Updates (Nicolas and all) + priorities definition
• New radii for UHV flange: 4x 3D models to update
-
type A and D2 to be done
-
type B is done
• Absorber covers: 3D still ongoing
-
springs fixation preliminary design done
-
more detailed 3D will be available --> action Nicolas
-
spring properties to be checked with supplier (Feuerherdt) --> action Gerhard
• Cooling tubes length
-
implemented already on tubes parts (assemblies and 2D drawings to be updated) --> will be completed before the review, action Nicolas
• Transition for D2
-
following the BS modification, transitions to be modified, 3D done, 2D done, action close
-
Michal confirmed to Nico Kos that BPM change has been completed (action for BI in ECR)
• New Reinforcement supports (4 designs)
-
3D for 4 types done
-
2D for two types done
• Modification of main body A for cooling reinforcement
-
3D done, 2D to be done
• New Feedthrough for D2
-
waiting for next iteration (drawing to be released asap, waiting for the next iteration from procurement process feedback)
• Update of D2 main body external dimension (140->130mm) + inner changes
-
3D done, 2D to be done (maybe already done, to be checked --> Nicolas)
• Welding machines integration study
-
drawings exist for Type B (ready by Friday evening --> Nicolas)
-
drawings and 3D for Type A --> to be checked
-
D2 --> 3D and 2D
-
hide all the non-completed parts from integration models --> action Nicolas, this was agreed with Delio
-
3D views with welding machines to be prepared for the review --> action Nicolas
-
• Comments on Heeral test bench
-
-
low priority
-
Electrodes Design (Michal)
was not discussed