Collision with survey reserved space (cooling coming from the roof: could be a showstopper!, maybe the vacuum gauge too, depending on its type);
Cooling power needed still under investigation; if we need cooling water <27 degree, a solution needs to be found to route it from the gallery to the detector without compromising survey needs to align the machine in the BGV areas.
Collision between largest ring and B2 bake-out jacket: see with them if this is a problem (B2 beam pipe bake-out not possible when the detectors are in place).
No direct answer yet, to be asked.
Tasks list:
BGV team: Ask Thibaut to confirm if we can remove BQK (possibly BPLV too?)
Helene had email confirmation from Thibaut that the BQK H and V will be moved to point 1 or point 5. Nothing concerning BPLV.
BGV team: ask VSC
If a new sectorisation should be done; if so how much would it cost
No sectorisation is not a showstopper; it seems that there is very little space to do it and it would greatly increase the costs.
If no new sector for the BGV: How often may this sector need to be baked-out due to other equipment in place?
No direct answer, but it didn't seem to be a worry. The vacuum sector is already quite short.
If the impossiblity to bake-out the B2 chamber while the detector is in place is a worry (how often would B2 chamber need to be baked-out)
No direct answer yet, to be asked.
What type of gauge would be installed on the tank; try to keep it out of the survey reserved space (current solution for the demo: 90deg elbow)
No direct answer yet, to be asked, but a similar solution than on the demo could be done.
What level of ancillaries is required by VSC (place needed, for bake-out equipment and pumps: required power, is it sufficient at the new location -> contact EN-EL: Nuno Dos Santos)
No direct answer yet, to be asked.
How much longitudinal space they wish to make the interface btween the BGV and neighbour equipments
No direct answer yet, seems to be ~200mm according tothe distance between equipments on the layout .
Teresa:
Adjust the exact longitudinal position of the instrument once this is fixed.
Also consider machine coordinate system: 1407, and that the integration models are in 1401. A change of reference system from 1407 to 1401 must happen.
Include vacuum gauges in both flanges of the vaccuum tank (even though it´s just needed one, the other is spare).
Check supports accessibility for adjustment purposes.
BGV team and Teresa: discuss with BE-GM how to include alignment targets: discuss the rigidity of the support of the target and see what is needed from survey point of view (preliminary: just identify possible problems and showstopper; a more detailed study can be done after the review). The geometers must be placed inside the red volume to allow alignment during operation.
BGV team, Teresa: estimate place needed for detector readout and cables; possibly include it on the drawings
BGV team: share any feedback on the Integration note; maybe start thinking of gallery aspects, although no showstopper is expected there
There are minutes attached to this event.
Show them.