Approval of previous minutes and review of actions15m
Summary of Actions :
B955 roof : Elsa informed us that for the leak on the roof of B955 the installation of an external scaffolding is foreseen (has been installed) to investigate possible consolidations – Elsa
Lifting beam: Julien will organize a follow-up meeting inviting also Serge Pelletier - Julien (see presentation today - CLOSED)
EN-CV cartridges - Continue looking for more efficient handling and transport solutions, including the use of a curtain-side truck and, where possible, pallets with appropriate support to optimise the available space - Sarah Moralent / Cédric Halbert / Serge Pelletier
BA80 - Communicate the relevant worksite constraints on a weekly basis, as precise transport time slots cannot be communicated sufficiently in advance - Anastazja Sedzicka.
Late request ID481 - Clarify the situation regarding the proposed storage of the power converters in front of B961 and identify possible alternatives before any storage solution is validated - Sarah Moralent
Prepare a dedicated presentation on the ZE and MSE supports and the lifting beam for the next TASK FORCE meeting - Will Edward John Townley - See presentation today - CLOSED