ADTC meeting
Puma LS3 Planning
Mark presented PUMAS's preliminary planning for LS3, including a transport to Isolde and the need to reduce the frame weight by one ton to meet crane limits. Mark indicated the continuous need for services such as cooling water (not mandatory but appreciated) and electricity. A recurring issue with the SEM grids was reported, where the beam is not visible when slowed down, possibly due to cable routing and induced signals..
AEgIS LS3 Activities
Gosia outlined AEgIS plans for LS3, which include both technical and scientific activities. A major technical activity is the opening of the full experiment as of Feb 2027 and the expected installation of a cryocooler on the 5 Tesla magnet to reduce liquid helium consumption. This will require significant additional electrical power and will be dependent on securing the remaining half of the funding. The positronium source is expected to be active throughout 2027, requiring electricity and cooling services.
GBAR LS3 Planning and Linac Operation
Jean-Yves discussed GBAR plans for LS3, which include improving the positron line and the trap. He also mentioned the possibility of changing an electrode in the HFT trap and the need for water and electricity for Linac operation. Francois reminded the electricity cuts expected for the AUG tests (26th January 2027). There is no LINAC maintenance plan for 2027, and the collaboration is expected to have more news on the expected continuation of the experiment early 2027.
AOB: ELENA Works and Vacuum Incident
Francois showed updates on the upcoming works on ELENA, starting on 1st December with the venting of the LNS line for the repair of ZQNA0020. A new request from Antoine to perform a test on the ion switch was discussed, but it was concluded that the test would take place only at the restart of ELENA in March 2028. A new activity has been added in the planning for the realignment of the LNE.ZDFHK.5101, taking advantage of the LNE50 line venting to correct this long-standing known roll alignment error.
Laurette mentioned a recent incident with a primary pump failure in the injection line, which caused a vacuum loss and required reconditioning of the ion switch. The team managed to recover the vacuum and restart beam operation on Wed morning. As a compensation, GBAR will get beam over the week-end before the end of the run on Monday at 18:30.