All coils apertures are complete but last 3 ones are left. It was decided to put on hold thise 3 apertures as they include biggest coils, waiting the LMBRD1 cold MM test results benchmarking from April.
Growth of a2 harmonic is expected on those apertures with pairing big and small coils resulting in shift of mid plane.
MBRD3 assembly about to be completed
MBRD4 to be assembled till April 25.
ECR on swap of 50 microns QH insulation layer will be drafted by INFN
MBRD3 inspection by INFN this week including documentation check,
MBRD3 shipment from mid February to B180
MBRD4 APs in sleeves, WMM performed last week
SM18 test plan meeting being resumed with TM section from end January once draft is available according to last
Closing of NCRson MBRD3-VS06 being finalised with last INFN comments (EDMS 3087008)