Due to POPS delay, schedule is still being reviewed.
From the LLRF side approximately 4-weeks of parallel testing of the cavitiy controllers in bld. 151 is needed. (In shadow of normal high power test).
Dedicated high power test to be performed as late as possible.
Actions:
Finish synoptics with addition of the AVC surveillance. (Ben)
Define new timings and send list to CO for implementation. (Heiko)
Produce flow-chart centred on the PLC. Show all relevant signals and the sequence needed to pulse the cavity. (Pierre + Ben + Heiko).