CTA deployment meeting

Europe/Zurich
600/R-001 (CERN)

600/R-001

CERN

15
Show room on map
Michael Davis (CERN)
    • 14:00 14:10
      Getting PUBLIC into Production 10m

      Status Updates

      • Spinner space is configured with GC. GC has been tested.
      • n_TOF (spinner space): tests can proceed
      • COMPASS (spinner space): queued for recall tests
      • DUNE: needs XRootD TPC to be configured on PUBLIC instance.
      • AMS: Vova will create a ticket for auth issues
      • NA61/SHINE: setting up their DAQ system + storage
      • TOTEM #277. 24 tapes from public_user need to be repacked. 0.5 PB of files in EOS need a tape copy. VM with SLC5 needs to access data on tape.
      • /afsmigration #282
      • Repack of LEP-era data. A further 247 tapes need to be repacked (engineering and nomad_delayed) #240

      TO DO

      • Finish repack of public_user (~1 month)
      • Migrate data from legacy experiments
      • Schedule next SME migrations after NA62

      Schedule

      • w/c 15 March: migrate NA62 to CTA
    • 14:10 14:20
      Getting LHCb into Production 10m

      Status

      Post Migration

      • DAQ integration and testing, including FTS Archive Monitoring
      • April: LHCb will stage small amounts of data for validation prior to reprocessing, then start pre-staging for their reprocessing campaign which will begin in May.
    • 14:20 14:30
      CTA Software 10m
      • Vlado and Julien to highlight high-priority issues which need development effort
      • Broad review of open tickets and set priorities over next few weeks, in preparation for arrival of fellows in April
    • 14:30 14:35
      AOB 5m