Speakers:
Domenico Giordano
(CERN),
Gonzalo Menendez Borge
(CERN)
Benchmarking Collection Campaign
- The end of the campaign is nearing
- Most of the sites have already finished 🏁
- 3 sites running the last HEPscore scripts
- 1 site is still in SPEC. Hurry up! ⏰
- Check machine configurations for missing entries
- Screenshot attached
- If the machine model is available, help is appreciated even if you have completed the campaign 😃
HEP-Workloads readiness
- IGWN:
- Validated. Ready to be executed for the 'matrix'
- Clarification needed about the limit of 80% of load reached (Josh is checking with the IGWN sw developers)
- Alice gen-sim-reco
- Reco step continues to fail. Alice experts are investigating.
- Meanwhile the Alice gen-sim-digi WL container image has been released
- Validation of Alice gen-sim-digi already started
- Atlas real-reco
- New WL proposed by Atlas.
- Build procedure in place, but still fails for an issue in the Atlas DB file (being fixed by Walter)