L4 Instrumentation Status
→
Europe/Zurich
Description
L4 schedule
HWC : 26 JAN–1 FEB (to L4 Dump). -- 5 days (Morning and Afternoon shifts)
BI HWC check list as defined by OP (L4/PSB MPC #51 HWC) will be:
- BCTs (Calibration + acquisition)
- Wire scanner (Moving control + acquisition)
- Wire grid (Moving control + acquisition)
- BSM (Moving control + acquisition)
- BPM (Calibration + acquisition)
- BLM (acquisition)
Schedule foreseen for BI devices is 26 JAN→27 JAN:
• Local timings , Specific applications , Oasis signals , Samplers , SIS
Beam Commissioning: 2 - 14 Feb
Details to be circulated by Piotr. Milestones and key dates should be:
- First week: go to 160 MeV with 2021 settings
- 09 Feb cavity re-phasing
- 14 Feb Beam Commissioning to LBE
- 21 Feb Beam to PSB
----> See attached Slides, updated Jan 28