HWC : 26 JAN–1 FEB  (to L4 Dump). -- 5 days (Morning and Afternoon shifts)

BI HWC check list as defined by OP (L4/PSB MPC #51 HWC) will be:

  • BCTs (Calibration + acquisition) 
  • Wire scanner (Moving control + acquisition) 
  • Wire grid (Moving control + acquisition) 
  • BSM (Moving control + acquisition) 
  • BPM (Calibration + acquisition) 
  • BLM (acquisition)

Schedule foreseen for BI devices  is 26 JAN→27 JAN:

•    Local timings , Specific applications , Oasis signals , Samplers , SIS 


Beam Commissioning:  2 - 14 Feb

L4/PSB MPC #51 

Details to be circulated by Piotr.  Milestones and key dates should be:

  • First week: go to 160 MeV with 2021 settings
  • 09 Feb cavity re-phasing 
  • 14 Feb Beam Commissioning to LBE
  • 21 Feb Beam to PSB

---->  See attached Slides, updated Jan 28


BI ISTs @ OP web tool check lists


 

Zoom Meeting ID
69627692777
Host
Federico Roncarolo
Useful links
Join via phone
Zoom URL
    • 1
      BCT - WD

      HW and SW readiness

      • IST results, any open issue

      • any request (and proposed plan) for special checks/tests during HWC or Beam Commissioning (following 2021 experience and/or YETS changes)
        -- timing, gating, any other setting ?

      Speakers: Athanasios Topaloudis (CERN), Miha Dolenc (CERN), Romain Brice Ruffieux (CERN)
    • 2
      BPM - ToF

      HW and SW readiness

      • IST results, any open issue

      • any request (and proposed plan) for special checks/tests during HWC or Beam Commissioning (following 2021 experience and/or YETS changes)
        -- timing, gains, calibration, any other setting ?

      Speakers: Ana Guerrero Ollacarizqueta (CERN), Michele Bozzolan (CERN)
    • 3
      BSM

      HW and SW readiness

      • IST results, any open issue

      • any request (and proposed plan) for special checks/tests during HWC or Beam Commissioning (following 2021 experience and/or YETS changes)
        -- timing, gating, any other setting ?
        -- ask for xx hours as soon as we have 160 MeV to re-tune RF sweeps and secondary electrons steering?

      Speakers: Jocelyn Tan (CERN), Mark Mclean (CERN), Stephane Bart Pedersen (CERN)
    • 4
      BSG - BWS -LASER EM - BTV

      HW and SW readiness

      • IST results, any open issue

      • any request (and proposed plan) for special checks/tests during HWC or Beam Commissioning (following 2021 experience and/or YETS changes)
        -- timing, gain, any other setting ?
        -- BWS: double check OP takes ref measurements with MEBT V scanner before and after swapping chopper polarity (up-down)
        -- assuming all ok for SF test stand BTV ?

      Speakers: Ana Guerrero Ollacarizqueta (CERN), Aurelie Noelle Goldblatt (CERN), Christophe Vuitton (CERN), Jean Tassan-Viol (CERN), Stephane Bart Pedersen (CERN), Stephane Burger (CERN)
    • 5
      BLM

      HW and SW readiness

      • IST results, any open issue

      • any request (and proposed plan) for special checks/tests during HWC or Beam Commissioning (following 2021 experience and/or YETS changes)
        --thresholds setting status?

      Speaker: William Vigano' (CERN)