WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up
zoom
CERN
Minute 31
Summary of actions treated :
- Plug-in design green light because no levelling decision
- Mechanical table assembly procedure next week
- Hydro bellow convolution under metrology - potential design modification
- Thermal treatment of jaws copper parts
- Remaining some parts from mech. table to control
- Planning : +15 days for tank and jaws and table, warning about the assembly
Summary of actions to have for proto :
- Installation procedure to redact
- Bellows RGA required after last leak tests
Summary of actions to have for serie :
- Find a better way to clean CuCd blocks
- Improve spec of bellows concerning validation tets and cleaning
Link to EDMS minutes : https://edms.cern.ch/ui/#!master/navigator/document?D:100889947:100889947:approvalAndComments