WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

Minute 45 

Mechanical table assembly:

  • Ultrasound test + visual inspection

TCC:

  • Leak on the rigid connection between test bench and tubes
  • Thermocouples arriving in 2 weeks

Design:

  • Jaw lifting tool production ongoing by STI
  • Jaw and tank procedure to update in 4 weeks

Absorber materials update:

  • CuCD blocks under metrology because new thermal treatment, impedance has to check if the porosity is a matter for them. Sent back 2 (or3?) blocks because parallelism not acceptable (70um, 60um), report attached to Indico
  • Carlotta and Jorge are visiting the company – they would like to understand difference between Nanoker and CERN metrology as well as other technical subjects

VSC:

  • Waiting for costs and delays
  • Design modifications due to holes position – 3D sent to Luca
  • Check an arrangement between STI and VSC to order one time for all the components

Production:

  • Bellows on shaft end by Tuesday, then cleaning and FE end of next week, welding on tank in 3 weeks then leak tests
  • Contouring tank plate done, cleaning done, welding FE next week (tank assembly for September)
  • First batch of jaw parts sent to STI
  • Beam pipes cut, to go to carbon deposit
  • BPM flange at 40/30 for leak tests for the repaired ones, now only 1 leak, to be repaired
  • Cooling pipes ok even with 0.2mm of flatness on the border. 2 last in metrology then leak test, ultrasound report 0.7mm mini thickness. Action for Dylan : check the mini thickness on the drawings, Fede can try to have the information
  • LHCTCLPX__0021 x2 to metrology, LHCTCLPX__0020 x2 50% done, then metrology for 3 weeks
  • LHCTCTPXH_0024 x2 to cleaning, accepted even being out of tolerance in the functional position + LHCTCTPXH_0072 75% done, end beginning of next week and LHCTCTPXH_0027/28 waiting, available in 6 weeks

Additional screws:

  • We now have 4x3 screws: Rollvis, Schaeffler, Ewellix, and maybe Moog

Graphite tapering:

  • Metrology good, but not for 28.9mm of height, and this is quite ok for impedance
  • A gap of 0.05mm for the serie is not mandatory
  • A quotation of 4 more is sent to Graphitech

Update on planning:

  • Update the jaw planning regarding the input of Emilien

Update for the serie:

  • Add the need to control the jaws parts in the functional position

Others:

  • RGA final report almost done (done)

Tools for flatness measurement: check the compatibility (point 4 or 132

There are minutes attached to this event. Show them.
    • 15:00 → 15:15
      Copper parts Prod planning 15m
      Speaker: Emilien Rigutto (CERN)
    • 15:15 → 15:30
      CuCD status 15m

      • Nombre de blocs en cours d’usinage, et résultats actuels
      • planning détaillé validé avec Nanoker
      • liste détaillé et planifiée des activités après la livraison au CERN.

      Speaker: Carlotta Accettura (Politecnico di Milano (IT))
    • 15:30 → 15:45
      Ongoing topics 15m
      Speaker: Dylan Baillard (CERN)