WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

MINUTE 46

Mechanical table assembly:

  • Cycling ongoing but under visual inspection for the moment

TCC:

  • Leak on the rigid connection between test bench and tubes
  • Thermocouples arriving in 1 weeks

Design:

  • Jaw lifting tool production ongoing by STI
  • Jaw and tank procedure to update in 4 weeks
  • 0.05 flatness in CZ for LHCTCTPXH_0021 can be enlarged, but we gain almost nothing for prod so we stay as we are

Absorber materials update:

  • Check the Carlotta’s attached document – Some work to improve the cleanliness of the process
  • Delays need to be checked

VSC:

  • Waiting for costs and delays
  • Design modifications due to holes position – 3D sent to Luca
  • Check an arrangement between STI and VSC to order one time for all the components
  • 15th of July reception of jackets
  • Prod of autoregulated testbench for the serie

Production:

  • Bellows on shaft end by Tuesday, then cleaning and FE end of next week, welding on tank in 3 weeks then leak tests
  • Contouring tank plate done, cleaning done, welding FE next week
  • First batch of jaw parts sent to STI
  • Re-machine 6 RF finger of each reference to be tested
  • Beam pipes under metrology before carbon deposit
  • BPM flange at 40/30 for leak tests for the repaired ones, now only 1 leak, to be repaired
  • Cooling pipes ok even with 0.2mm of flatness on the border. 2 last in metrology then leak test, ultrasound report 0.7mm mini thickness. Action for Dylan : check the mini thickness on the drawings, Fede can try to have the information
  • LHCTCLPX__0021 x2 to metrology, LHCTCLPX__0020 x2 50% done, then metrology for 3 weeks
  • LHCTCTPXH_0024 x2 to cleaning, accepted even being out of tolerance in the functional position + LHCTCTPXH_0072 75% done, end beginning of next week and LHCTCTPXH_0027/28 waiting, available in 6 weeks

Additional screws:

  • We now have 4x3 screws: Rollvis, Schaeffler, Ewellix, and maybe Moog

Graphite tapering:

  • A quotation of 4 more is sent to Graphitech

Update on planning:

Update for the serie:

  • Update the leak test tool for bellow production for the serie
  • Nourrice to re-design because there is too much leaks and not easy for pumping

Link to the EDMS minutes : https://edms.cern.ch/ui/#!master/navigator/document?D:100889947:100889947:approvalAndComments