MINUTE 47 

Mechanical table assembly:

  • Cycling ongoing but under visual inspection for the moment

TCC:

  • Leak on the rigid connection between test bench and tubes
  • Thermocouples arriving in 1 weeks
  • New screen to check with Paolo

Design:

  • Jaw lifting tool produced by STI
  • Jaw and tank procedure to update in 4 weeks

Absorber materials update:

  • Check the Carlotta’s attached document – Some work to improve the cleanliness of the process
  • CuCD blocks for first jaw S33 with 1 spare, rest of the blocks ready for S40 (blocks 4 and 5 relatively good)
  • Delays need to be checked

VSC:

  • Waiting for costs and delays
  • Design modifications due to holes position : invert the male and female part because the pins are too long : ok for protos  
  • Check an arrangement between STI and VSC to order one time for all the components
  • 15th of July reception of jackets
  • Prod of autoregulated testbench for the serie

BI:

  • EDMS 2419688 for the ABCD convention: same as CEM
  • A discussion is needed to check with CEM the viability of the proposition
  • ABCD stay fix and thanks to that we know which BPM is on which jaw and upstream or downstream

Production:

  • Bellows on shaft end by Tuesday, then cleaning and FE end of next week, welding on tank in 3 weeks then leak tests
  • Tank waiting for FE, then FE for bellows assemblies
  • Jaw copper parts TCTPXH n.1 finished and the rest before the Fabrice’s holidays
  • Action for Dylan : give to Emilien which reference of RF finger to produce for tests and quantities
  • BPM flange at 40/30 for leak tests for the repaired ones, now only 1 leak, to be repaired
  • Manifold from STI almost done + lot of other parts

Additional screws:

  • We now have 4x3 screws: Rollvis, Schaeffler, Ewellix, and maybe Moog

Graphite tapering:

Update on planning:

Update for the serie:

  • Let the Combitac in the initial position for the serie
  • Update the leak test tool for bellow production for the serie