WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

MINUTE 48

Mechanical table assembly:

  • Cycling launch to 10k

TCC:

  • The TCC test bench burned
  • Action: have as soon as possible a quotation for a chiller
  • Do not touch in any case the TCC because we need the data of LS2 collimators (TCSPM and TCPPM)
  • Steven received the inputs and specification to design a new posing system for the jaws
  • Carlotta needs thermocouples at the inlet and outlet of the jaw circuit

Design:

  • Jaw lifting tool produced by STI
  • Jaw and tank procedure to update in 4 weeks

Absorber materials update:

  • Update second Nanoker visit : if we have them W39, this is good. We can release the CuCD lateral face flatness, it can avoid grinding on it. Check report 2757736

VSC:

  • Waiting for costs and delays
  • Design modifications due to holes position: invert the male and female part because the pins are too long : ok for protos
  • Check an arrangement between STI and VSC to order one time for all the components
  • 15th of July reception of jackets
  • Prod of autoregulated testbench for the serie

BI:

  • EDMS 2419688 for the ABCD convention: same as CEM
  • A discussion is needed to check with CEM the viability of the proposition
  • ABCD stay fix and thanks to that we know which BPM is on which jaw and upstream or downstream

Production:

  • Mistake on the cooling pipes : Wrong diameter in the beginning/ end of the pipes -> solution is to add an longer fitting ring, thanks to that we can use the leak test tool
  • Bellows on shaft end by Tuesday, then cleaning and FE end of next week, welding on tank in 3 weeks then leak tests
  • Tank under EB welding + re-machining of the bellow shaft next week
  • Jaw copper parts TCTPXH n.1 finished and the rest before the Fabrice’s holidays
  • BPM flange at 40/30 for leak tests for the repaired ones, now only 1 leak, to be repaired
  • Manifold from STI almost done + lot of other parts

Additional screws:

  • We now have 4x3 screws: Rollvis, Schaeffler, Ewellix, and maybe Moog

Graphite tapering:

Update on planning:

Update for the serie:

  • Remove the surfacing of the bellow for the serie, this is useless
  • Be aware of the penetration of the welding in the drawing, this is written 3 and 6mm but this is 6mm everywhere

Link to EDMS minutes : https://edms.cern.ch/ui/#!master/navigator/document?D:100889947:100889947:approvalAndComments

There are minutes attached to this event. Show them.
    • 14:00 → 14:20
      Design of the TCC by Steven : spec + inputs 20m
    • 14:20 → 14:45
      Ongoing topics 25m