MINUTE 49
Mechanical table assembly:
- Cycling to 10k finished, Windows update stopper the cycling.
TCC:
- The TCC test bench burned
- 2 quotations ongoing from Julabo and Huber
- Do not touch in any case the TCC because we need the data of LS2 collimators (TCSPM and TCPPM)
- Steven received the inputs and specification to design a new posing system for the jaws
- Carlotta needs thermocouples at the inlet and outlet of the jaw circuit (fast response better)
Design:
- Jaw lifting tool produced by STI – cleaning ongoing
- Jaw and tank procedure to update in 4 weeks
Absorber materials update:
- Blocs 4, 5, 6 received and bloc 3 sent back because of porosity. Blocs 7, 8, 9, 10 under control, they send it by the end of next week. Vacuum test of the 7 blocks planned mid of August
VSC:
- Waiting for costs and delays
- Check an arrangement between STI and VSC to order one time for all the components
- 15th of July reception of jackets
- Prod of autoregulated testbench for the serie
- How VSC find a leak on the BPM flanges?
- Graphite tapering RGA -> to check the feasibility, Carlotta and Fede give the input of a 1200°C TT for 72h. This may be interesting to check if the temperature of time can be less : we can do the first reliable solution for 4 of them regarding the planning and then the 2 ones with the gap of 0.2mm can be tested differently.
BI:
- A discussion is needed to check with CEM the viability of the proposition
Production:
- Mistakes on the 2 tanks: TCTPXH tank in finition process, the thickness of the bottom plate is 0.6mm under the nominal value -> Solution: add thick washer between tank plot and mechanical table. TCLPX tank bottom plate welded in the wrong sense at 180° -> Solution: Remove the end plates, remachine them and keep the tank extremities and re-weld the new plate + cleaning
- Mistake on the cooling pipes: Wrong diameter in the beginning/ end of the pipes -> solution is to add an longer fitting ring, thanks to that we can use the leak test tool
- Bellows on shaft end by Tuesday, then cleaning and FE end of next week, welding on tank in 3 weeks then leak tests
- First cooling pipes brazing finished -> leak test
- RF fingers additional production ongoing
- Re-machining of the bellow shaft this week
- Jaw copper parts TCTPXH n.1 finished + 4 TCTPXH parts under metrology
- Last BPM flange repaired but VSC find a new leak on one of them -> reparation at the workshop
- Manifold from STI done + lot of other parts
Additional screws:
- We now have 4x3 screws: Rollvis, Schaeffler, Ewellix
Graphite tapering:
Update on planning:
- Adding delays on the tank regarding Emilien inputs
Update for the serie:
Link to EDMS minutes : https://edms.cern.ch/ui/#!master/navigator/document?D:100889947:100889947:approvalAndComments
There are minutes attached to this event.