WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

MINUTE 49

Mechanical table assembly:

  • Cycling to 10k finished, Windows update stopper the cycling.

TCC:

  • The TCC test bench burned
  • 2 quotations ongoing from Julabo and Huber
  • Do not touch in any case the TCC because we need the data of LS2 collimators (TCSPM and TCPPM)
  • Steven received the inputs and specification to design a new posing system for the jaws
  • Carlotta needs thermocouples at the inlet and outlet of the jaw circuit (fast response better)

Design:

  • Jaw lifting tool produced by STI – cleaning ongoing
  • Jaw and tank procedure to update in 4 weeks

Absorber materials update:

  • Blocs 4, 5, 6 received and bloc 3 sent back because of porosity. Blocs 7, 8, 9, 10 under control, they send it by the end of next week. Vacuum test of the 7 blocks planned mid of August

VSC:

  • Waiting for costs and delays
  • Check an arrangement between STI and VSC to order one time for all the components
  • 15th of July reception of jackets
  • Prod of autoregulated testbench for the serie
  • How VSC find a leak on the BPM flanges?
  • Graphite tapering RGA -> to check the feasibility, Carlotta and Fede give the input of a 1200°C TT for 72h. This may be interesting to check if the temperature of time can be less : we can do the first reliable solution for 4 of them regarding the planning and then the 2 ones with the gap of 0.2mm can be tested differently.

BI:

  • A discussion is needed to check with CEM the viability of the proposition

Production:

  • Mistakes on the 2 tanks: TCTPXH tank in finition process, the thickness of the bottom plate is 0.6mm under the nominal value -> Solution: add thick washer between tank plot and mechanical table. TCLPX tank bottom plate welded in the wrong sense at 180° -> Solution: Remove the end plates, remachine them and keep the tank extremities and re-weld the new plate + cleaning
  • Mistake on the cooling pipes: Wrong diameter in the beginning/ end of the pipes -> solution is to add an longer fitting ring, thanks to that we can use the leak test tool
  • Bellows on shaft end by Tuesday, then cleaning and FE end of next week, welding on tank in 3 weeks then leak tests
  • First cooling pipes brazing finished -> leak test
  • RF fingers additional production ongoing
  • Re-machining of the bellow shaft this week
  • Jaw copper parts TCTPXH n.1 finished + 4 TCTPXH parts under metrology
  • Last BPM flange repaired but VSC find a new leak on one of them -> reparation at the workshop
  • Manifold from STI done + lot of other parts

Additional screws:

  • We now have 4x3 screws: Rollvis, Schaeffler, Ewellix

Graphite tapering:

  • Procurement ongoing

Update on planning:

  • Adding delays on the tank regarding Emilien inputs

Update for the serie:

Link to EDMS minutes : https://edms.cern.ch/ui/#!master/navigator/document?D:100889947:100889947:approvalAndComments

There are minutes attached to this event. Show them.
    • 14:00 → 14:45
      Ongoing topics 45m
      Speaker: Dylan Baillard (CERN)