MADMAX Preparation for YETS 22/23

Europe/Zurich
Zoom

Zoom

Minutes of the MADMAX CERN Meeting

Present: A. Dudarev, A. Rummler, A. Amamou, B. Rae, B. Majorovits, C. Krieger, D. Kreikemeyer, D. Kittlinger, D. Strom, D. Jaillet, J. Bernhard, J. Devine, J. Schaffran, M. Van dijk, M. Mentink, P. Pralavorio, T. Koettig, X. Genillon

 

1.) Introduction (J.Bernhard)

  • Alexander Gerbershagen left. New contact for 2023 campaign: Johannes Bernhard. For >=2024: Maarten Van Dijk
  • Planning discussion, possible window for magnet cooling + experiment could be 28.02.23 - 17.04.23 (preliminary and subject to change). Dates confined through cooling water availability in BA81 for the start and the beam commissioning in H8 for the end.
  • Contact for planning questions: Bastien.Rae@cern.ch, contact for installation questions: Michael.Lazzaroni@cern.ch.

2. MADMAX News (B. Majorovits)

  • Major milestones reached these last 12 months :
    • Magnet quench protection and conductor demonstrated to be feasible. Prototype magnet foreseen after 2026 at DESY
    • Booster mechanically feasible : i) piezo motor commissioned under strong B field and at 4K, ii) prototype with one disk (P200) run successfully in cryolab cryostat and at Morpurgo (inc. interferrometer).
    • Booster calibration full chain established with CB100
    • RFI compatibility established in Morpurgo (April 2022) --> can conduct long runs in Morpurgo
    • Prototype cryostat available mid 2023 in Hamburg
  • Morpurgo magnet is suitable to perform long time run for MADMAX prototypes

3. Morpurgo Magnet (A. Dudarev)

  • Apr. 2022 run : supply pressure to the magnet 200 mbar +/- 100. Not healthy and require to increase the speed of the pump close to the limit (55 cycle / minute)
  • Jun 2022: fix implemented on the cryo installation
  • Sep./Oct. 2022 : cool down the magnet and perform 3 tests to check that the fix solves the problem (and it did !) 
  • Xavier Genillon will provide a documentation to the users of the magnet
  • Not possible to run at 1.9 T (unless we have a very strong argument like an axion candidate to check)
  • Morpurgo magnet is ready for long / stable runs in 2023 with control given to the users

4. MADMAX 2023 CB Test Plans (D. Strom / B. Majorovits)

  • 2022 Morpurgo run allows to achieved the foreseen goals : 
    • No unwanted signals found mixing into the heterodyne system
    • The low nooise amplifier works at 1.6 T
    • No impact of Morpurgo on the DAQ
  • 2023 plans: 
    • Setup/takedown at CERN : 5 days
    • Measurement with CB100 in B-field : 4 days (min) to 4 weeks (max) (TBD)
    • May be some time with CB200 (TBC) ?
    • Requires magnet stable at 1.6 T and operated by users
  • Physics goals (2023-24):
    • Surpass CAST limit with CB100 (>=100 hours at 1.6 T) in 2023
    • Improve further the limit with CB200 and G10 cryostat in 2024 

5.a G10 Cryostat (D. Kreikemeyer)

  • Cheap solution to make cold test in 23 and 24 at Morpurgo (while waiting for the proto-cryo to arrive)
  • Commissioning of G10 cryo + CB100 ~ 1 week in 2023

5.b G10 Cryostat (T. Koettig)

  • Successful first attempts in the cryolab in summer 2022 to test Transfer Line option
  • Can Install and run the setup for the commissioning run in 2023
  • Possible to connect to the gazometer in the Morpurgo area
  • Cryocooler option can be envisaged in 2024.

6. MADMAX 2024/2025 Tests: Status of the Cryostat (C. Krieger)

  • Call for tender successfully concluded in Dec. 2021- : will be build by Bilfinger Noell GmbH
  • Received Final Design Report in August 2022 -->Start discussion with CERN safety before the end of the year
  • Receiver cryostat build at MPP
  • Rail system already at CERN, blessed by safety. Discussion ongoing for a dry run end of 2023
  • On schedule to start operation at Morpurgo in Dec.2024 

7. AoB

  • Letizia (CERN safety) in maternity leave. Johannes / James D. will report to the safety section
  • Technical and planning meetings in the mean time with smaller circle of involved persons.
  • Next meeting: Proposal for week of December 5th (doodle will be send)
There are minutes attached to this event. Show them.