WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up
→
Europe/Zurich
zoom (CERN)
zoom
CERN
14:00
→
14:45
Ongoing actions45m
Speaker:
Dylan Baillard(CERN)
MINUTE 71 :
LAST WEEK:
PT100 validation by VSC
TCTPXH jaw results
Gregory checks with Emilien to produce 1 short NEG Cartridge
RF fingers new design proposal for Luca under C1 -> target for Emilien: 26th of May
MME remaining parts to produce
OTHER ACTIONS:
TCC:
TCTPXH on the testbench on Monday and Tuesday
RF fingers:
RF fingers third cycling finished -> finger support broke around 10 and 12k cycles at several points. Check with Luca and Fede to maybe have only 1 opening. Annealing make the stripping impossible. The tests will determine the Ag thickness + annealing or not
TCTPXV review and modifications for serie: Emanuel working on it
TCLM masks: not started
Copper wedges for jaws posing during vacuum test (STI)
Assembly:
TCLPX to be be inserted
TCTPXH under vacuum test next week after TCC tests
Production MME:
Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118 -> flanges for proto S21, mock-up S24 with metrology + cleaning
BPM flanges: S14 machining - S15/16 : FE – S17 leak test – S17 delivery : currently under leak test
Cooling circuit : 3 received from ELI industries – little correction on a BPM – No delivery date to give for the moment (remaining steps : machining, metrology, brazing, cleaning, leak test, pressure test) -> not the priority (TCSPM first -> Régis estimate 3 or 4 weeks for Wyss waterjet cutting)
Cap + spacers + other collars (with electropolishing + rhodium): 6th of June
RF fingers for installation in the proto: Delivery dates when we get the confirmation from STI (depends a lot of the chemical cut, Emilien already possess several parts of the fingers -> Give the quantities and the drawing
Update on planning:
Collimators shall be operational for July.
RF fingers, PT100 and RF components on the critical path