WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

    • 14:00 → 14:45
      Ongoing actions 45m
      Speaker: Dylan Baillard (CERN)

      MINUTE 71 : 

      LAST WEEK: 

      • PT100 validation by VSC 
      • TCTPXH jaw results
      • Gregory checks with Emilien to produce 1 short NEG Cartridge
      • RF fingers new design proposal for Luca under C1 -> target for Emilien: 26th of May 
      • MME remaining parts to produce

       

      OTHER ACTIONS:

      TCC:

      • TCTPXH on the testbench on Monday and Tuesday 

       

      RF fingers:

      • RF fingers third cycling finished -> finger support broke around 10 and 12k cycles at several points. Check with Luca and Fede to maybe have only 1 opening. Annealing make the stripping impossible. The tests will determine the Ag thickness + annealing or not
      • Romain is preparing a report 

       

      Design 

      • TCLP, TCSPM, TCTPM folders: Ongoing. 
      • Post-proto modifications regarding Dylan’s Excel: Ongoing 75%
      • TCTPXV review and modifications for serie: Emanuel working on it 
      • TCLM masks: not started
      • Copper wedges for jaws posing during vacuum test (STI)

       

      Assembly:

      • TCLPX to be be inserted  
      • TCTPXH under vacuum test next week after TCC tests 

       

       

       

       

       

       

      Production MME: 


      • Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118 -> flanges for proto S21, mock-up S24 with metrology + cleaning 

       

       

      • BPM flanges : S14 machining - S15/16 : FE – S17 leak test – S17 delivery : currently under leak test

      • Cooling circuit : 3 received from ELI industries – little correction on a BPM – No delivery date to give for the moment (remaining steps : machining, metrology, brazing, cleaning, leak test, pressure test) -> not the priority (TCSPM first -> Régis estimate 3 or 4 weeks for Wyss waterjet cutting)
      • Cap + spacers + other collars (with electropolishing + rhodium): 6th of June 
        
       


       

      • RF fingers for installation in the proto: Delivery dates when we get the confirmation from STI (depends a lot of the chemical cut, Emilien already possess several parts of the fingers -> Give the quantities and the drawing

       

      Update on planning: 

      • Collimators shall be operational for July. 
        • RF fingers, PT100 and RF components on the critical path 

       

      Update for the serie:

      • May use 4 blocks instead of 8 for TCTPXH