WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

MINUTE 72 : 

LAST WEEK: 

  • Take back the gabarit to test the cooling 
  • TCTPXH jaw UHV acceptance test
  • PT100 acceptance test : Good, Gregory suggest to continue with the series production (on June)
  • MME remaining parts to be produced
  • Dylan shall prepare a procedure for PT100 + Sub-D9 cleaning 
  • Dylan shall prepare a procedure for RF fingers production
  • Dylan shall prepare a procedure for BPm flanges production 
  • Emilien shall send the BPM leak test report 
  • Hositrad flanges in June 

 

OTHER ACTIONS:

TCC:

  • Remi shall finish the procedure waiting for the last update from JMQ

RF fingers:

  • RF fingers fourth cycling -> finger support begin to be broken around 10 and 12k cycles at several points. Check with Luca and Fede to maybe have only 1 opening. Tests will determine the Ag thickness + annealing or not
  • Romain is preparing a report 

Design 

  • TCLP, TCSPM, TCTPM folders: Ongoing. 
  • Post-proto modifications regarding Dylan’s Excel: Ongoing 75%
  • TCTPXV review and modifications for serie: Emanuel working on it 
  • TCLM masks: not started
  • Copper wedges for jaws posing during vacuum test (STI)

Production MME: 


  • Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118 -> flanges for proto S21, mock-up S24 with metrology + cleaning 
  • Cooling circuit : 3 received from ELI industries – little correction on a BPM – No delivery date to give for the moment (remaining steps : machining, metrology, brazing, cleaning, leak test, pressure test) -> Not the priority (TCSPM first -> Régis estimate 3 or 4 weeks for Wyss waterjet cutting
  • RF fingers : Chemical cut of the figners support ongoing with a 3 fingers-opening, fingers under silver plating, then EBW -> 10+5 fingers support. Emilien is using the fingers already cut. For the proto we are using a 5um plating without annealing. 
  • Cap + spacers + other collars (with electropolishing + rhodium): 6th of June 
    2 rhodium parts available
  • RF fingers for installation in the proto: target 26/05, last date for project 09/06
  • 1 short NEG Cartridge -> reception date? S34 maximum regarding the planning 

 

Update on planning: 

 

Update for the serie:

     
   
   
    
  
 