PT100 acceptance test : Good, Gregory suggest to continue with the series production (on June)
MME remaining parts to be produced
Dylan shall prepare a procedure for PT100 + Sub-D9 cleaning
Dylan shall prepare a procedure for RF fingers production
Dylan shall prepare a procedure for BPm flanges production
Emilien shall send the BPM leak test report
Hositrad flanges in June
OTHER ACTIONS:
TCC:
Remi shall finish the procedure waiting for the last update from JMQ
RF fingers:
RF fingers fourth cycling -> finger support begin to be broken around 10 and 12k cycles at several points. Check with Luca and Fede to maybe have only 1 opening. Tests will determine the Ag thickness + annealing or not
TCTPXV review and modifications for serie: Emanuel working on it
TCLM masks: not started
Copper wedges for jaws posing during vacuum test (STI)
Production MME:
Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118 -> flanges for proto S21, mock-up S24 with metrology + cleaning
Cooling circuit : 3 received from ELI industries – little correction on a BPM – No delivery date to give for the moment (remaining steps : machining, metrology, brazing, cleaning, leak test, pressure test) -> Not the priority (TCSPM first -> Régis estimate 3 or 4 weeks for Wyss waterjet cutting
RF fingers : Chemical cut of the figners support ongoing with a 3 fingers-opening, fingers under silver plating, then EBW -> 10+5 fingers support. Emilien is using the fingers already cut. For the proto we are using a 5um plating without annealing.
Cap + spacers + other collars (with electropolishing + rhodium): 6th of June 2 rhodium parts available
RF fingers for installation in the proto: target 26/05, last date for project 09/06
1 short NEG Cartridge -> reception date? S34 maximum regarding the planning
Update on planning:
Update for the serie: