ERAM Meeting

→ Europe/Zurich
Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
    • 11:00 → 11:45
      ERAM status
      Conveners: Alain Delbart (Université Paris-Saclay (FR)), Dr David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
      • 11:00
        ERAM production status at Rui's lab 5m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Dr David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
        • No news from Rui, David tried to visit the workshop but everybody was on vacation
        • Alain asked again for the DLC foils baking, no news so far
        • Charlotte will go to the workshop to investigate the bulks, the date for the next detector to cabling
        • MM1-DLC2 cleaning should be done this week, it is the priority
        • ERAM-2, 10, 13 will be soon cleaned/tested (simple cleaning since these are just "dusty" and not in short-circuit
      • 11:05
        Mesh pulsing 10m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Dr David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
      • 11:15
        ERAM gluing 5m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), Dr David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
      • 11:20
        ERAM testing 10m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), Dr David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
        • David was at CERN last week
        • Noise on the test bench was fixed by removing and reconnecting the FECs. Not linked to the low voltage PS LAN connections
        • Ethernet cable changed on one of the PS, seems to still be working, should be fixed
        • Data for the electronics calibration at 0V/350V were taken, needs to be done again with different peaking times
        • Flow increased from 10 to 15L/h, dew point of -36C reached 
        • Calibration of the sensors to be checked, using the GMC sensor, the dew point sensor and the Arduino
        • Criterion to start a scan so far: 0.4 % RH on the Arduino, several runs were started with a maximum of 1% RH
        • Important parameter to watch is to keep a constant value of the humidity in the gas for a scan
        • Procedure proposal: large flow of Argon at ~20L/h to dry the gas for 24h, then switch to T2K gas at ~15L/h until you reach a plateau, procedure to be updated with flushing duration (4 volumes)
        • Current ambient humidity ~ 20% RH, was around ~50% RH last Summer: seems to have an impact on the humidity in the chamber
        • Add a line in the expert shifter instructions to give second green light before full scan that the plateau has been reached, and in the shifter instructions to check with the expert before starting the full scan
        • 10 bar gas still available at the moment, see AoB
        • Note : CERN MPGD asked us to be careful at the beginning of the operation of ERAM-16, ERAM-16 to be installed next by the end of the week, after the tests of electronics calibration
        • Cosmic data taking with field cage prototype and ERAM-30, trigger less noisy

         

         

         

      • 11:30
        ERAM AOB 15m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), Dr David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)

         

        • Gas available:
        • 1 full bank, to be connected the week of Feb. 13th
        • Gabriella's bank to be shipped back (empty), the 10 bar bank to be placed in its location, the full bank for the test bench to be placed in the current place of the 10 bar bank
        • 1 new bank to be ordered for the test bench Charlotte and Sandrine, bank type: SCEM 61.02.06.003.9
        • Need to localize the detectors on the mockup in the travelers
        • Clean room:
          • 1 cleaning this week if possible (not necessarily extremely thorough)
          • 1 full cleaning to be done soon
          • 1 cleaning after the insertion of the half field-cage in the clean room and 1 after the field cage is taken out of the clean room for ERAM operation
          • 1 cleaning every 3 weeks between 2 insertions of field cages
          • after FC out | 3wks | 3 wks | before FC in | 1wk | after FC out

         

        • Test of a half field cage: how to close on cathode side (need to dismount mockup?)