Critical issues until 2016

Participants: J. Barranco, B. Dalena, J. Esberg, B. Jeanneret, A. Latina, R. Lillestol, J. Pfingstner, G. Rumolo, D. Schulte, J. Snuverink, F. Stulle, Y.W. Wang

D.S. discussed the next steps which are required for the CLIC planning until 2016. Critical issues have to be identified and prioritized. A first list of work packages will have to be ready by beginning of March.
D.S. showed slides by L.R. regarding work packages for the main beam injector complex and slides by R.T. regarding the BDS.
A.L. discussed work packages regarding the low emittance transport. G.R. and F.S. commented on collective effects and the RTML.
B.J. discussed work packages regarding the drive beam complex.