ERAM Meeting
-
-
11:00
→
11:45
ERAM statusConveners: Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
-
11:00
ERAM production status at Rui's lab 5mSpeakers: Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
- 11:05
-
11:15
ERAM gluing 5mSpeakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
-
11:20
ERAM testing 10mSpeakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
ERAM 36 scan is still ongoing.
Full scan started on Saturday morning due to small issue with data taking time per pad. Expect it to be done by tonight.
From a look at about 3/4 of the full scan, we don't notice any top-bottom effect.
Plan for this week is to install ERAM 37 and do the scan. Laura will check with student (Shubham) if he can do the shift this week.
-
11:30
ERAM AOB 15mSpeakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
Last week moved to the new gas rack, after gas ran out towards the end of incomplete ERAM 36 shift.
Need to check how much gas is left and make sure we have enough for the next 10 detectors. Charlotte will check if we have a spare rack, and if not we should order one now so as not to use the same rack as the field cage. TBC with Alain.
Katharina will put ERAM 37 in the oven on Wednesday afternoon, so that it has time to dry bu Thursday. To be coordinated with David and Alain.
Installation will be done on Thursday.
From Alain's email on the QC of ERAM detectors to be mounted on FC
QC of eram in T2K gas will be replaced by a test in air : tuning of this test is on-going (tested on eram-35, eram-18, eram-34) by David. this test can be done before mounting on bottom tpc ( erams will be dried in oven at 50 degrees duruing one night) and after mounting (water adsorption seems to be very slow)
-