From: Oliver Boettcher
Sent: Friday, June 23, 2023 12:22 PM
To: Antonio Alonso <antonio.alonso@cern.ch>; Jaime Perez Espinos <jaime.perez.espinos@cern.ch>; Nikolaos Chatzigeorgiou <nikolaos.chatzigeorgiou@cern.ch>; Dirk Mergelkuhl <Dirk.Mergelkuhl@cern.ch>
Cc: Michel Raymond <Michel.Raymond@cern.ch>; Francisco Sanchez Galan <francisco.sanchez.galan@cern.ch>; Rita Perez Martinez <rita.perez.martinez@cern.ch>
Subject: WP8 visit for completing the ATLAS chimney cabling simulator - Notes and conclusions
Dear all,
Together with Jaime, Nikos, Dirk and Antonio we realized the visit of the ATLAS chimney mock-up yesterday 22/06/ and discussed the coordination of the cabling and the finishing of the ATLAS chimney cabling mock-up.
The attached presentation of Damien Bréthoux (presented at 126th HL-LHC WP8 Meeting, 28 February 2023) was used as support for the discussion.
This mail is to keep everybody updated and to circulate the main conclusions.
Take note as well that I created an Indico event for better tracking of our discussion:
https://indico.cern.ch/event/1300118/
We agreed on the following next steps:
- Until mid of July:
- WP8 finishes the ATLAS chimney region (some minor parts to be added and well we like to paint it in ATLAS blue)
- Until mid of August
- WP8 installs the ATLAS chimney mock-up to the VAX mock-up
- WP8 together with ATLAS and LUCID experts define the space reservation in the ATLAS chimney region for their cables
- WP8 integration designers develop a proposal for the VAX services passage through the chimney as well for the design of the supports and attachment to the VAX box.
- Based on b) and c) WP8 builds and integrates space reservation into the mock-up.
- As from mid of August – WP12 TE-VSC takes measures to integrate M1 cables to the mock-up (with respect to the space reservation for ATLAS and LUCID cables)
- As from mid of September – the robots team could realize Cranebot handling tests for M1 removal and installation
Depending on the results of the tests in this configuration, further decision can be taken related to the passage of services for M2 and M3 through the chimney and the possibility of separately removing M1 module as from Run4 during Technical Stops.
Other discussions, questions raised:
- During scenario discussions of how to remove M2+M3 together with the VAX box, Dirk raised the question if it’s assured that the TX1SP Plug shielding can be removed with the Big Wheel in open position.
I stated that this would be the case, however the ATLAS configuration for every scenario got still to be checked and validated. (WP8 will realize a scenario analysis together with TE-VSC and ATLAS.) - Jaime stated that VAX service cables and pipes will be supplied by WP12, Connectors also those required on top of TX1S monobloc for the removal of M2+M3 need to be provided by WP8. (Oliver shares with Francisco.)
- The question came up if the VAX region is designed for ATLAS A-side is a mirror of ATLAS C-side or if both sides are just turned and exactly the same. This question is relevant for the design of the VAX box, the service guidance and supports.
From several points it would be very helpful to have the same design for A and C side and not a mirror situation. Jaime stated that also the question of having spare modules is connected to this. (Oliver checks with Michel and Francisco.) - Together with Dirk we came to speak about the fiducialisation of the TAXS. Jaime explained the engineering and design approach of the M1 connection to the TAXS chamber.
Survey measurements will be required to check the correct connection of M1 to the TAXS chamber and fiducialization should be done consistent with this requirement. (Dirk and Jaime to decide if fiducialization should be integrated to the VAX mock-up for eventually realize tests.)
Please feel invited to return your comments or corrections to these notes.
Best regards,
Oliver Boettcher
(CERN BE-EA-EC / HL-LHC WP8)