ISOLDE Technical Coordination Meeting

→ Europe/Zurich
508/1-001 (CERN)

508/1-001

CERN

20
Show room on map
Zoom Meeting ID
69900009564
Host
Joachim Vollaire
Useful links
Join via phone
Zoom URL
    • 14:00 → 14:05
      Minutes - Introduction - Review of agenda¶ 5m

      Follow-up of last meeting :
      -50 kV limit from SY-ABT ?
      -Water infiltration no obvious link with scaffolding of handrail on top of Building 170
      -Interlock matrix for GPS, HRS and MEDICIS Frontends is now on EDMS (BE-OP-ISO informed)

      For information, SY-BI camera (tubes) not used anymore by BE-CEM for target changes (no optimization and replacement done this YETS). System (expensive to maintain) might be removed in the future.

    • 14:05 → 14:10
    • 14:10 → 14:20
      Updated on YETS activities for REX&HIE ISOLDE 10m
      Speaker: Erwin Siesling (CERN)
    • 14:20 → 14:25
      Update on facility commissioning - OP report + BTY commissioning plan 5m
      Speakers: Alberto Rodriguez (CERN), Eleftherios Fadakis (CERN), Emiliano Piselli (CERN), Erwin Siesling (CERN), Joachim Vollaire (CERN), Miguel Luis Lozano Benito (CERN), Simon Mataguez (CERN)
    • 14:25 → 14:30
      RILIS 5m
      Speakers: Cyril Bernerd (CERN), Katerina Chrysalidis (CERN), Reinhard Heinke (CERN)
    • 14:30 → 14:35
      MEDICIS & Building 179 5m
      Speakers: Charlotte Duchemin (CERN SY/STI/RBS), Laura Lambert (CERN), Ralf Erik Rossel (CERN)

      MEDICIS:

      • At MEDICIS this week the maintenance of the access system is ongoing. Once done Didier Chapuis will sign the beam permit. The MEDICIS DSO tests are planed for Thursday morning. These tests won't affect the target area but we will probably need to go to S6 to be able to reach the decay point, that was modified to be declared as a safe position. Anne will test this new functionality.
      • From Tuesday next week we will start the commissioning of the facility with the conditioning of the electrode and then proceed with the first stable beam production.
      • Next week we would also like to have one pulse 3E13 ppp on one of our gaf chromic by sending the sample holder on the low trolley, to verify the good positioning of the beam for that position.

       

      Building 179:

      • Last week we had a VIC with CV with regardes to b.179 cooling upgrades. No dates yet, but to be anticipated likely sometime in May. 1 day shut down with no access to the building required - this date is flexible.
      • Mia's Pa-231 arrives today with source loading going on tomorrow.
      • Update on water leaks, Aurelien in contact and waiting for a response from contractors, work estimated on the roof mid-april -> this work will have no impact on facility operations.
      • Nano/MEDICS water purging -> to be tested this week once we have the OK from Seb/Bernard on carburisation completion.
    • 14:35 → 14:40
      Targets and Schedule update 5m
      Speakers: Hanne Heylen (CERN), Mia Au, Sebastian Rothe (CERN)

      Targets:

      #851-VD5 

      This target has an external sample of only 1E15 Atoms. 

      TISD team will take care of all heating LINE and TARGET, gas and the rest.

       

      CaO nano production started. Setup is being prepared.

      La Liquid: Material has been procured.

       

      Actinide production 179 nanolab:

      - During testing of the new controller somme bugs were identified and are being adressed. UC and ThC produciton will continue in the evening.

       

      Schedule

      Part II ongoing.

    • 14:40 → 14:50
      Safety 10m
      Speakers: Alexandre Dorsival (CERN), Elodie Aubert (CERN), Nadine Conan (CERN), Simon Mataguez (CERN)
    • 14:50 → 14:55
      AOBs and visits 5m

      Beamgates (S.Rothe)

      • Voltage dividers for monitoring HT arrived, will be tested at Offline2 this week
      • Then system moves to ISOLDE 
      • Verified availability of power outlet (behind mag 90) 

      • Suggest to create impact for installation and debugging. 
      • 3 spare BNC signal cables identified - could be used for signal or monitor
      • Beamgate logic controller will be moved to a free network outlet in RA9 in OICR.

       image-2024-3-26_10-50-54.png

      • Working set got an addition for the Beamgate control

       

      - expert gui in progress.