ISOLDE Technical Coordination Meeting
-
-
14:00
→
14:05
Minutes - Introduction - Review of agenda 5m
Minutes
Review of agenda
Any special to discuss before -
14:05
→
14:10
Update on YETS activities in the primary areas 5m
-
14:10
→
14:20
Updated on YETS activities for REX&HIE ISOLDE 10mSpeaker: Erwin Siesling (CERN)
REXTRAP:
Status report from Fredrik:
- The REXTRAP cage has been cleaned, gas injection reconnected, PSUs switched on
- Thursd 14 March Fredrik tried to restart the different PSUs, but there are still some that can’t be controlled; Lefteris is following up.
- Local ion source was heated up to 10 W, and after a major outgassing peak, things stabilized.
- Once the control problem is sorted out, one should get beam through asap. Fredrik recommends to use QP arrays as given in:
https://logbook.cern.ch/elogbook-server/GET/showEventInLogbook/3861316
https://logbook.cern.ch/elogbook-server/GET/showEventInLogbook/3857718
- When there’s a window Fredrik would like to carry out some verifications of voltages in the extraction region.
REX/HIE ISOLDE:
- Cryo discovered a broken turbine on the coldbox last week – replaced and filter changed as well
- Time used to change an oil pump on the compressor station
- Cryo interventions set back the schedule by 2-3 days (start cooldown sequence starts Thursday 21st March instead of Monday 18 March)
- Access to the tunnel roof by Cryo from time to time (move line pump)
- Access tunnel for the Survey team – verification CM and elements positions (before cooldown starts) -intervention will finish Tuesday-morning 19 March
- HEBT lines survey verification also ongoing for which the fuses are pulled and switches turned off on the mezzanine (HIE elements) – interventions will finish (before) Thursday 21 March
- REX RF running between access’s
HIE SRF:
- Due to absences, an alternative SRF startup team has been formed (Walter Venturini, Matthieu Therasse, Akira Miyazaki – from Orsay (only 1 week))
- SRF systems are being restarted. Low power (~1 Watt) will be applied to test the chain and start first RF setting-up measurements.
PUMA preparational work:
- Modification of the ISOLDE overhead crane (installation power bus-bar + reel) is being discussed to postpone to YETS 24/25 – too many safety constraints with the HIE ISOLDE SC Linac in cooldown sequence
WISARD handling:
- Modification to their small crane was supposed to happen in the shadow of the main overhead crane work. With the postponed overhead crane work and start of the WISARD experiment beginning of May in mind we prefer to postpone also the modification of the crane (which requires high scaffolding and blockage for several days of the overhead crane) to the YETS 24/25
- Safety inspection/discussion on the WISARD procedure to handle the inner part of their structure took place Monday 18 March – intermediate solution (until crane is at correct height) has been found: A small platform with garde-corps will be constructed to able handling on the top of the magnet (Pascal Catherine).
-
14:20
→
14:30
Operation Report 10mSpeakers: Alberto Rodriguez (CERN), Eleftherios Fadakis (CERN), Emiliano Piselli (CERN), Erwin Siesling (CERN), Joachim Vollaire (CERN), Miguel Luis Lozano Benito (CERN), Simon Mataguez (CERN)
Target Operation
HRS
- #593-MK1(W) : Was mounted to HRS, open circuit detected , replaced with #734-Ti-MK1(Ta) which has a K mass marker.
- HRS Gas System Expert interface works, need to test gas system after the target change
GPS
- #837-UC-VD5 : did not couple to FE after 2 attempts. Decided to use #592-VD5 instead.
- Installed noble gas mix bottles on GPS, adjusted the pressure to 1.3 bar. (CF4 and Ar are on HRS.)
- GPS Gas System Expert interface works for GPS
-
14:30
→
14:35
RILIS 5mSpeakers: Cyril Bernerd (CERN), Katerina Chrysalidis (CERN), Reinhard Heinke (CERN)
-
14:35
→
14:40
MEDICIS & Building 179 5mSpeakers: Charlotte Duchemin (CERN SY/STI/RBS), Laura Lambert (CERN), Ralf Erik Rossel (CERN)
This week at MEDICIS, is devoted to the Patch Panel Installation and yearly checks by Julien Parra-Lopez. In order to connect the patch panel, the two gas systems had to be dismantle yesterday (will need to be reinstalled by Friday). Intervention in the bunker is planed for tomorrow by EN-EL due to an issue spotted by Melania.
In parallel, RP team is checking the RP monitors in building 179 in preparation for the DSO tests.
Next week Didier CHAPUIS will do his yearly maintenance of the access system (Monday and Tuesday + Wednesday as back-up). He would like to access this week on friday afternoon.
The DSO tests to obtain the hardware and beam permits are foresseen for Thursday 28th of March at 9 am. Anne Funken will sign the beam permits in the afternoon max. (if no big surprises).
The week after (from 2nd of April) the commissioning period with stable beam will start, starting from Ralf and Laura (with the help of Elena and Line if needed) that everything restarts properly. The first step is to condition the new electrode with the HV and then perform calibration checks with Sm and Tb, including laser tests.
On 4th of April we would need to get one pulse of 3E13 ppp on one gafchromic to verify the good positionning of the beam when shooting on the low trolley.
-
14:40
→
14:50
Targets, Schedule and Physics 10mSpeakers: Hanne Heylen (CERN), Isabel Frank (CERN), Mia Au, Sebastian Rothe (CERN)
-
14:50
→
14:55
Safety and AOBs 5mSpeakers: Alexandre Dorsival (CERN), Elodie Aubert (CERN), Nadine Conan (CERN), Simon Mataguez (CERN)
Beamgates
- Beamgate logic hardware tested and validated at Offline 2 .
- Communication via CMW, Knobs will be configured by L.Le.
- Most likely required expert interface development via MTA
- Beamgate HT switches: Waiting for High Voltage divider to test analog readback to Beamgate controller.
Others
- Water infiltration in the hall reported (water coming down along the wall at the location of the HT room entrance)
- SSP lab HPGe unavailable for upcoming collections - next step to find an alternative solution / location?
-