CMS Flushing system update

Europe/Zurich
CERN

CERN

Beatrice Mandelli (CERN), Pablo Marin Barbancho (CERN)

CMS Tracker system

Present: Patrick, Gianluca, Beatrice, Pablo, Pier Giorgio, Lazar

https://indico.cern.ch/event/1372843/

 

Electrical status

  • missing profibus cable to order: problem since it will be outside building: Pier Giorgio will check with Siemens
  • list of cables provided by Patrick to Pablo
  • electrical connectors under Gas team responsibility 

 

Surface system

  • missing some info from Gas Team: mapping of top of the racks with all dimensions and diameters of the pipes —> Andrea
  • types of connectors on top of the rack —> Andrea

 

UX system

  • 4 racks foreseen
  • electrical cabinet instead of rack
  • P&ID to check between Gas team and Pablo —> Andrea to organise a meeting
  • 3D drawings to prepare —> Mattia

 

Piquet

  • Underground system —> in M&O of gas system
  • surface system: on best effort and to train people for basic operation by Andrea: Pablo to prepare a list of persons for training

 

WorkPackage

  • to update based on Pablo’s comments —> beatrice
  • to add piquet —> Beatrice
  • to update FSU table: missing info for mechanical and weld —> Andrea
  • to update electrical hardware list —> patrick
There are minutes attached to this event. Show them.