CMS Tracker system
Present: Patrick, Gianluca, Beatrice, Pablo, Pier Giorgio, Lazar
https://indico.cern.ch/event/1372843/
Electrical status
- missing profibus cable to order: problem since it will be outside building: Pier Giorgio will check with Siemens
- list of cables provided by Patrick to Pablo
- electrical connectors under Gas team responsibility
Surface system
- missing some info from Gas Team: mapping of top of the racks with all dimensions and diameters of the pipes —> Andrea
- types of connectors on top of the rack —> Andrea
UX system
- 4 racks foreseen
- electrical cabinet instead of rack
- P&ID to check between Gas team and Pablo —> Andrea to organise a meeting
- 3D drawings to prepare —> Mattia
Piquet
- Underground system —> in M&O of gas system
- surface system: on best effort and to train people for basic operation by Andrea: Pablo to prepare a list of persons for training
WorkPackage
- to update based on Pablo’s comments —> beatrice
- to add piquet —> Beatrice
- to update FSU table: missing info for mechanical and weld —> Andrea
- to update electrical hardware list —> patrick