ROC Managers' Meeting
Tuesday 17 Apr 2007, 11:00
→
12:30
Europe/Zurich
CERN
CERN
Nick Thackray
Description
Actions
, https://edms.cern.ch/document/753089
Minutes
, https://edms.cern.ch/document/829338
This meeting is 09:00 to 10:30 UTC (11:00 to 12:30 Swiss local time). Phone number is: +41 22 767 6000 Access code is: 0147097 Or click here:
https://audioconf.cern.ch/call/0147097
The conference call opens 5 minutes before the meeting starts.
11:00
→
12:30
ROC Managers' Meeting
11:00
Admin matters
5m
Quarterly Report
Meetings:
Note change of day for next meeting -
Wednesday 2 May
Milestones
Deliverables
Moderators
Speaker
:
Alistair Mills
document
11:00
Feedback on minutes of last meeting
1m
11:05
GGUS reports
10m
Speaker
:
Diana Bosio
TPM Monitoring
TPM Report
GGUS ticket escalation report
Report
11:15
Site down-time procedures & tools
15m
Proposed EGEE Procedures for Service Interruptions
Speaker
:
Maite Barroso
Proposal for site downtime broadcasting and reporting
Speaker
:
Helene Cordier
Slides
11:30
Review of failover plans for operations core tools
15m
Wiki page is here:
http://goc.grid.sinica.edu.tw/gocwiki/Failover_mechanisms/
11:45
Request for all ROCs to populate the list of internal SA1 issues
1m
The list can be found here:
https://twiki.cern.ch/twiki/bin/view/EGEE/SA1_Internal_Issues
Speaker
:
Nick Thackray
11:45
Tier1 weekly availability graphs in RC reports
1m
Speaker
:
Maite Barroso
Slides
11:45
Updates to the operations manual
1m
The updates are highlighted via this link:
https://twiki.cern.ch/twiki/bin/rdiff/EGEE/EGEEOperationalProceduresDraft?rev2=4&rev1=10&render=sidebyside
The summary is:
Change of references from SFT to SAM
Info about Removing resources (not sites)
Between 2nd and 3rd escalation step if the site responds but the problem still persists the COD suggest to site to go to downtime.
Ticket should not expire during weekends and CODs do not have responsibilities during weekends.
Security issues are not responsibilities for COD.
Certificate validity test.
Tickets should be reopened only if they are about the same problem.
SAM alarm generation procedures.
Speaker
:
Ioannis Liabotis
11:50
EGEE related projects: SEEGrid operations
30m
Speaker
:
Ognjen/Antun
Slides
12:20
Review of action items
5m
list of actions
12:25
AOB
5m