HL-LHC TDE Preliminary Design Review

Europe/Zurich
CERN

CERN

Patrick Goodwin Hurh (Fermi National Accelerator Lab. (US))
Description
Background
 

The High Luminosity (HL) upgrade to the Large Hadron Collider (LHC) will increase each beam’s maximum stored energy from 540 MJ (current Run 3) to 710 MJ. The LHC has two Target Dumps External (TDEs), one for each counter-rotating beam. The purpose of a TDE is to safely and reliably absorb the LHC beam at any time, while not restricting the nominal minimum interval between dump events. Simulations and material studies proved that the current Target Dump External design would not be compatible with the more stringent operating conditions imposed by the HL upgrade. 

A new TDE design, compatible with HL-LHC beam parameters, has been developed and is the subject of this review. Developments have been made in beam-matter interaction studies, thermomechanical simulation, CFD analysis, material studies and prototyping, design and integration studies together with hardware prototyping.


Basis of the Review

The LHC beam dump core can be summarised as consisting of four major subsystems, the purpose of each is explained here:

  • Core: absorb a majority of the incoming beam’s stored energy.
  • Vessel: contain the core and the inert atmosphere required to prevent the core material oxidising; facilitate heat transfer between the core materials and the outer atmosphere; allow the incoming beam to enter the core materials.
  • Support structure: hold the vessel in place and maintain its alignment with the beam; mitigate and withstand the intense beam-induced vibrations of the vessel.
  • Cooling system: cool the TDE sufficiently to prevent overheating in the case of repeated, high intensity beam impacts.

The fundamental requirements of the HL TDE system are stated in the Functional Specification (EDMS 2694263).

In this Design Review (DR), the design that has been developed to meet the requirements of HL will be presented in detail. The maturity of the design in each area is dependent on the subsequent timescales for procurement and implementation. In the areas of the core and vessel, the design will be fully defined, and this will act essentially as a manufacturing readiness review. In other areas, such as the cooling system, this will act as a preliminary design review as there may still be further refinements and detailed design aspects to develop.

The estimated lead times for the principal components of the TDE core and vessel are 12-18 months. Orders for these parts must be placed in summer 2025 to meet the installation deadlines for the HL TDEs.

A Systems Engineering (SE) approach has been adopted to structure the design process. The necessary functions of the system were derived from design requirements from several sources. A Failure Modes and Effects Analysis (FMEA) was used to identify the critical functions of the system and the key risks, enabling prioritisation of design studies and a thorough understanding of the system’s vulnerabilities.


Mandate

The panel shall assess whether the proposed design and project schedule is compatible with the project requirements, so that the procurement and construction for the series units can continue as planned. The panel shall determine if additional studies or design modifications are needed to ensure that the TDEs for HL meet all design requirements and maintain an acceptable level of risk in view of the design failure cases. The panel is requested to provide a summary of the review outcome in the form of a document to be submitted to the HL TDE project leader, WP14 leader, HL-LHC management and SY-STI management within ten working days from the end of the review.


Composition of the Review Panel

1. Patrick Hurh, FNAL (Chair)

2. Michael Fitton, STFC

3. Drew Winder, ORNL

4. Stefano Sgobba, CERN

5. Michele Modena, CERN

Linkpersons: Gabriel Banks (SY-STI) & Nicola Solieri (SY-STI).


Charge Questions

The Review Panel members are asked to answer the following questions:

1. Assess and challenge the presented design requirements. Have they been correctly understood by the design team and have any design requirements been not appropriately considered or missed?

2. Does the design that has been presented fulfil all design requirements?

3. Is the design feasible to procure, manufacture, assemble, test and install in the time available and with the logistical constraints of HL?

4. Were the key technical, project and operational risks properly identified, and have they been adequately mitigated by the proposed design and the design studies performed? Are the residual risks acceptable?

5. Concerning the simulation package that contributes to the proposed design: are the assumptions, inputs and interpretation of the outputs valid? Are there any outstanding items that may have been overlooked?

6. Has an appropriate level of quality control been adopted throughout the design process?

7. Review the way that experimental or test results have been used to inform design decisions. Were the assumptions made appropriate and have the results been interpreted correctly?

8. Are there any obstacles that prevent the design that has been presented moving forward with the first steps of series production? If yes, make recommendations of further work that should be completed before these can commence.

9. For areas where the design is less mature and the production does not yet need to start, is the current design and R&D going in the right direction to be ready for procurement to commence?

10. Is the current proposed spare strategy adapted to the identified risks, long term degradation mechanisms and use of the allocated budget?

Registration
Registration form
  • Tuesday 11 March
    • 08:30 08:50
      Introduction the review and to the HL-LHC beam dumps project 20m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map
      • High-level introduction of the TDE: key functions and location
      • High-level introduction to the dump (shape, contents, key challenges)
      • Objective of the review
      • Recall Previous challenges and developments:
        o Original dump history
        o Challenges during Run 2
        o LS2 upgrades
      • Introduce reviewer’s questions
      • Introduce agenda and tie the reviewer’s questions to contributions
      • Acknowledgements
      Speaker: Nicola Solieri (CERN)
    • 08:50 09:10
      LHC Beam Dumping System (LBDS) 20m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      A description of the LHC Beam Dumping System, of which the beam dump block (TDE) is a key component.

      • Introduction to LHC extraction system
      • Components of LBDS
      • Beam parameters and filling schemes expected for HL
      • Failure modes
      Speaker: Chiara Bracco (CERN)
    • 09:10 09:40
      Systems Engineering 30m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Description of the systems engineering approach taken in the design of the HL TDE.

      • Sources of requirements
      • Requirements gathering and processing
      • Regulatory context
      • Overview of requirements database (functional requirements and related performance requirements)
      • FFMEA process overview, results and conclusions.
      • Explain how requirements (and implicit DFMEA aspects) will be introduced in the remaining topics of the review.
      Speaker: Gabriel Banks (CERN)
    • 09:40 10:05
      Energy deposition studies 25m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Description of beam-matter interaction studies performed as the basis for the HL TDE design.

      • Setup of different models used
      • Material properties
      • Breakdown of total energy deposited by component
      • Energy density profile for nominal, full intensity dump event
      • LBDS failure scenarios results and conclusions
      • Other conclusions
      Speakers: Anton Lechner (CERN), Helene Guerin
    • 10:05 10:25
      Coffee break 20m 30/7-018 - Kjell Johnsen Auditorium - Annex

      30/7-018 - Kjell Johnsen Auditorium - Annex

      CERN

    • 10:25 11:15
      Carbon-based materials for TDE core 50m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      A description of the design process followed to arrive at the current proposed design of the TDE core.

      • General requirements for core materials
      • Market Survey process (inputs and assumptions)
      • Material testing
      • HiRadMat-65 experiment approach, assumptions, analysis, QA + results
      • Refinement of material distribution following HRMT results
      • Describe validation checks and calculations
      • Detailed geometry of IG and CFC parts and features introduced to mitigate possible failure modes
      • CFC shrink fitting feasibility studies and simulations
      • FMEA – residual risks in design following mitigation
      Speaker: Gabriel Banks (CERN)
    • 11:15 12:20
      Thermo-mechanical assessment of the dump core 1h 5m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Overview of the thermo-mechanical calculations and simulations undertaken to substantiate the current proposed design for the TDE.

      • Recall requirements of vessel and core
      • Overview of Run 3 design, material properties, dynamic response load cases, stress analysis
      • Description of the new proposed design, geometry, materials, response and stress analysis.
      • Detailed description of simulation approaches, model setup, assumptions and simplifications, mesh and post processing.
      • Studies of other operational scenarios
      • Conclusions, appropriate mitigation of possible failure modes, residual risks.
      Speaker: Asbjoern Lund
    • 12:20 12:40
      Q&A 20m
    • 12:40 13:40
      Lunch break 1h
    • 13:40 14:20
      Vessel prototyping and material testing activities 40m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Description of prototyping activities and material testing completed, their conclusions and impact on the proposed design.

      • Titanium procurement
      • Manufacturing process used and material tests performed
      • Shrink fitting procedure and results
      • Welding
      • Testing of 318 LN fatigue properties at elevated temperatures, fracture toughness and welding development
      Speaker: Asbjoern Lund
    • 14:20 14:50
      Welding 30m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Overview of developments in welding approach and geometries informing proposed TDE design.

      • Overview of current welding solution adopted in Run 3 beam spares
      • Ti Gr 5
        o Electron beam welding specification, joint geometry and parameter development
        o Qualification welding results
        o Production process for HL dumps
        o Other welding options
      • 318LN requirements and process developments
      Speaker: Umberto Bagnolo
    • 14:50 15:20
      Support system 30m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Description of support system design, analysis and proposed upgrades

      • Requirements, constraints
      • Components of cradle and interfaces with shielding and dump
      • Thermo-mechanical assessment of run 3 support system
      • Stress mitigation proposals
      • Detailed analysis of cables, lubrication and radiation hardness
      • Critical failure modes and mitigations
      • Summary of proposed HL design + remaining work required for detailed design
      Speaker: Asbjoern Lund
    • 15:20 15:50
      Coffee break 30m 30/7-018 - Kjell Johnsen Auditorium - Annex

      30/7-018 - Kjell Johnsen Auditorium - Annex

      CERN

    • 15:50 16:10
      Compliance with applicable CERN safety regulations 20m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map
      Speaker: Gabriel Banks (CERN)
    • 16:10 16:50
      Cooling system simulations 40m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Overview of cooling system studies completed and conclusions for HL design.

      • Requirements
      • Description of current operational cooling system and limitations
      • Benchmarking of run 3 model
      • Detailed simulation setup
      • Performance comparison of different upgrades and implications for operation
      • Feasibility of different options, comparison in terms of work needed, integration issues, cost, RP issues.
      • Conclusion on proposed configuration
      Speaker: Giovanni Binda Notarianni (ETH Zurich (CH))
    • 16:50 17:15
      Preliminary implementation of cooling system upgrade 25m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      Overview of cooling system studies completed and conclusions for HL design.

      • Requirements
      • Description of current operational cooling system and limitations
      • Feasibility of different options, comparison in terms of work needed, integration issues, cost, RP issues.
      • Conclusion on proposed configuration
      Speaker: Francesco Dragoni (CERN)
    • 17:15 17:45
      Detailed design studies 30m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map

      A description of the detailed design studies performed to refine the HL TDE geometry

      Speakers: Marc Timmins (CERN), Vincent Maire
    • 17:45 18:05
      Q&A 20m 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      190
      Show room on map
    • 18:05 18:35
      Executive session 30m
      Speaker: Nicola Solieri (CERN)
  • Wednesday 12 March
    • 08:40 09:00
      Opening of day 2 20m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      Opening comments from panel for day 2. Reminder of any outstanding actions from day 1. Overview of day 2 agenda.

    • 09:00 09:30
      Instrumentation package 30m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      Details of instrumentation design proposed for HL

      • Overview of past and operational instrumentation suites
      • Return of experience, reliability, interpretation and usefulness
      • Proposed instrumentation suite for HL and work required.
      Speaker: Enrico Bravin (CERN)
    • 09:30 10:00
      Radiation protection 30m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      Radiation protection assessments done for HL TDE upgrade.
      - Radiation protection requirements
      - Assessment of proposed design against requirements
      - Residual dose rate for different intervention scenarios (cooling times)
      - Air activation UD cavern (1 vs 2x flowrate)
      - Waste disposal
      - Argon content and spilling
      - Ti vs SS comparison
      - LS3 intervention scenario

      Speaker: Dr Angelo Infantino (CERN)
    • 10:00 10:20
      Conceptual design of the argon system 20m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      Description of preliminary design of controlled argon atmosphere and related safety systems for HL TDE.

      • Nitrogen system implementation in Run 3
      • Consumption of nitrogen over runs - reasons and challenges
      • RP requirements
      • Design of new system and expansion vessel, integration
      Speaker: Gabriel Banks (CERN)
    • 10:20 10:45
      Coffee break 25m 30/7-010

      30/7-010

      CERN

      30
      Show room on map
    • 10:45 11:10
      Procurement and production plan. Overall project plan. 25m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      Description of procurement and production plan related to the proposed design.

      • Components of dump design
      • Production strategy and procurement path for each component
      Speaker: Nicola Solieri (CERN)
    • 11:15 11:45
      Cost estimate and spares strategy 30m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      Cost estimate for proposed design, sources and assumptions.

      Available budget for HL TDEs and how it will be used

      Spares strategy
      - Why spares are required
      - Reasons for proposed number of spares
      - Strategy - how the spares would be produced, stored and used if needed.

      Speaker: Nicola Solieri (CERN)
    • 11:45 12:00
      Closing remarks and final aspects required for full detailed design 15m 30/7-010

      30/7-010

      CERN

      30
      Show room on map

      For those components where there are still some actions required to reach a detailed design, explanation of the steps required to arrive at the detailed design, assumed deadlines and any potential risks

      Speaker: Nicola Solieri (CERN)
    • 12:00 13:50
      Lunch break 1h 50m
    • 13:50 17:00
      Closed session for panel 3h 10m 30/7-010

      30/7-010

      CERN

      30
      Show room on map
    • 17:00 17:30
      Closing and initial comments from panel 30m 30/7-010

      30/7-010

      CERN

      30
      Show room on map