IBDRS internal water drains and poured concrete

→ Europe/Zurich

Presents: Johan, Ida, Martin, Fabio, Claudio, Edouard, Stefano

Internal water drains:

- water collector under the dumps:

  • the first idea was to connect this collector to the robot trench but this implies drilling works into the faraday cage (slides 2-3-4)
  • after discussion the variant to use the room under the HRS faraday cage seems better (slide 7)

 

- general water drains:

  • into this room it can be installed a tank (or two) with a pump connected across the target area to the retaining tanks in 179-R-403
  • an RP assessment is necessary to check if the water pump can survive in this room (high level of radiations) - Fabio
  • water grid collection points in can be installed on level zero of bulding 738 to drive the water into this room (slide 7)
  • CE will study more in details this soluton - Martin

 

GPS poured concrete:

  • presentation of step by step poured concrete installation (slides 9 to 13)
  • on the first 800 mm layer (yellow in slide 6) there is no necessity to make a slope but some small chanels can drive wate to the drains
  • this will facilitate the iron blocs installtion on a good and flat surface
  • the concrete shall be poured progressively layer after layer, not in one monoblock
  • verify if we can reuse some old concrete blocs to reduce the volume of poured conctrete - Stefano-Ana Paula
  • the planning shall be modified to allow CE to pour the concrete in coordination with the installation of the blocs by HE - Simon
  • verify the real interest to have a 2nd niche (slide 13) close to the HRS faraday cage (for special targets and wastes) ? -Stefano-Joachim-target peoples
  • the same study shall be done for the HRS side - Stefano

 

Kind regards,

Stefano