IHEP MCBRD Project weekly meeting record of minutes
- MCBRD5 was not measured magnetically at RT due to material issue at IHEP, to be measured at CERN
- WMM reports of MCBRD6 and 7 are being uploaded by IHEP on MTF
- Table of fiber glass details update was shown per aperture and shall be uploaded in MTF
- Cold test of MCBRD6 being resumed after thermal cycle this week
- NCR on CB22 updated by IEHP with decision not ot use CB22 aperture in magent assembly, being uploaded for CERN approval