IHEP MCBRD Project weekly meeting

Europe/Zurich

Record of meeting

 

  • CB24 training test complete with 147 quenches ot 530A, waiting decision to pair it with CB22 in MCBRD8, NC to be reopen for its use.
  • CB25 shos remarquable low training, best over all production, only 20 quenches to 500 A. This aperture had Fiber insulation layers adapted following 04/2024 CERN visit. Some issues appeared on the insulation of VTs and IHEP shall open an NC to trace and check if it is reparable ( next week after warm up). Yingzhe ot send updated FG insulation table with CB25 check
  • CB26 is about to be VPI impregnated thies month
  • CERN asked ot update drawing IHEP 0064 of Ultem cover to avoid remachining it at CERN on next magnets