Present: M. Bozzolan, H. Damerau, A. Findlay, T. Levens, O. Marqversen, B. Woolley
- Agreed exploitation model for the pick-ups used by RF in PSB and PS
- Equipment responsibility for the chain from pick-up, through head amplifier and cables should be in BI, up to the level of the delivery of the beam signal to RF. This also includes pick-ups used for the transverse feedback.
- Operational responsibility, which mainly means exchanging head amplifiers, should be with RF. Spares, repair, any future development, etc. will be taken care of by BI.
- The budget for future cabling activities will be agreed between BI and RF groups on a case-by-case basis.
- Follow-up: Heiko to update the tables on the codimd https://codimd.web.cern.ch/Pew9LWP_Q4qIvSIHZ5Hk7A accordingly.
- PSB
- For the phase pick-ups (beam control) a new head amplifier developed by Michele is presently under test on ring 4. New cables have already been pulled to one (out of four) phase pick-up stack. Once fully commissioned, it is planned to equip a second stack with the new amplifiers, for which also new cables will have to be pulled (post LS3?). Follow-up: BI and RF to agree on cost sharing.
- While the pick-up of transverse feedback is under BI responsibility, RF should take care of the kicker (still the initial installation from early 1980s). The spare situation for pick-ups and kickers is unclear, but likely none are available. Follow-up: BI and RF will try to find out if any spares do still exist. Follow-up: BI will check if a special pick-up and head amplifier is still required or if the present situation is only for historical reasons. A replacement by a standard pick-up and/or head amplifier should be considered, otherwise a CONSolidation request to rebuild a spare should be made. Follow-up: Without a kicker spare, RF to make a CONsolidation request to rebuild a spare, or joint request with BI for pick-up and kicker consolidation. Follow-up: RF to confirm that the functionality of the BOSS can be implemented in the digital signal processing of the transverse damper LLRF, at latest with the next generation transverse dampers.
- PS
- The development of the new head amplifier needed to replace PU83/PU93 by PU39/PU79 is being finalized and validation with beam is foreseen at the end of the 2025/beginning of the 2026 run.
- For the beam signal to the transverse feedback system the operational responsibility (exchange of the head amplifier) should be with RF. Spares, repair, any future development, etc. will be taken care of by BI. Follow-up: BI to check if the new standard PS head amplifier developed by Michele, would also be suitable for the transverse feedback.
- The hybrids for the PS radial loop pick-ups are under responsibility of BI. In the longer term (post-LS3), the hybrids will be superseded by the new head amplifiers (internal hybrids) for all pick-ups. Follow-up: BI to clarify the spares situation and eventually procure spare hybrids. Follow-up: BI to check the cost of new cables to five location of dedicated radial loop pick-ups (22, 36, 51, 76, 96). BI and RF to find a budget solution to have cables pulled with the recabling campaign of the CODD pick-ups already in the pipeline.