IBDRS HRS Boris Tube shielding proposal

→ Europe/Zurich

Presents: AP. Bernardes, S. Mataguez, J. Dauge, G. Cnudde, C. Cipriani, N. Quinquis, S. Marzari

  • 2 variants presentation by Stefano
  • We don't have clear information in archives 
  • Looking at the old pictures there is probably a reinforced layer of concrete around the Eternit tube
  • This Eternit tube is embleded and in direct contact with the concrete around it
  • Under the Boris tube there is most probably also poured concrete
  • The same metodology was probably used on GPS Boris tube
  • An additional poured concrete volume on the side of the GPS dump has to be removed after the dump removal
  • An inspection of these poured concrete shall de done quickly after earth removal
  • The base line is to not desmolish the poured concrete around the Boris tube and pour new concrete steps on top of it (Variant 1)
  • The remaining volume will be filled with standard blocs
  • This variant 1 will not delay the planning
  • SCE will check in archives if more infos are available
  • Nicolas will prepare an option B for GPS dismantling taking into account that blocs are stack in poured concrete.