(1) Review on production done so far, with details in durations with respect to targets
(2) Dependencies:
Components:
- List of components that are still not in-house
- Remind on what was critical in the past and what can be still critical
Services:
- Show all the people that need to intervene along the construction process (MME/VSC/Busbars/Electrical Technicians/X-Rays...)
(3) Work organization and potential bottlenecks: how work is organized, how different teams are called to intervene and where things can be improved. Is there potential to advance some preparation activities with less experience personnel? If yes, what would be useful?
Include an assesment of what would be needed if Q1/Q3 needs to be cryostated at CERN, and what is the differenc in terms of workload for a full cryostating of a Q1/Q3 unit vs a change from transport to test configuraiton/
(4) Quality conntrol and assurance, procedures and tracking
(5) Budget and Resources (Staff, grads, M4P, MAT)
(6) Space