Update on on-going activities:

 

  • Racetrack coil mock-up
    • The mock-up was returned from the oven on July 16, however, no data has been obtained as of yet.
    • Set-up: 1 pin on fixing the fixed pole to the mold, 2 pins + 1 screw fixing the floating pole to the mold -> Gap measurements are consistent.
    • Gap change should be compared with other racetrack coils.
    • Reaction mold disassembled:

The first pin was easily removed by hand, the second was removed with the aid of tools, and the third fractured during the extraction process. A weak point in the pin can be the source of this.

    • Check if it was the right size of the pins.
    • Currently, the mold is placed in the polymer lab and leak tight.
    • Alternatives for epoxy for impregnation is going to be looked into.
    • Aiming for injecting the coils next week in the polymer lab.
    • Winding of the second one, to be scheduled for second half of August.

 

  • Splicing sequence
    • The length of the splice was increased with 20 mm, resulting in an 17 mm increased length overall for the Sarcophagus. Some modifications on the Sarcophagus needs to be done.
    • Production of the Sarcophagus: Drawings needs to be modified due to increased length. Need to find thermo-couple, possibly buy a standard one and modify it.
    • Tinning: New cutting method. Action: need to find proper material for the blades. Consider adding screws and spring.
    • Splicing: Nothing new.

 

  • BOND Structure overview of where we are:
    • Components: Coil components for reaction ordered, 3 sets. Coil components for final coil, missing the instrumentation.
    • Winding tool: Progress is in price inquiry.
    • Reaction tool: Reaction mold is in the same package as the rest, but did some modification to increase the splice.
    • Guiding table for reaction mold: Waiting for calculation, Federico has no time until possibly next week. Aiming to be done with drawings in one week.
    • Sarcophagus: Drawing was ready but now it needs to be updated. Fabrication outside CERN, price inquiry needs to be done.
    • Splicing: study is done, 2D drawing is missing.
    • Impregnation mold: Under study
    • Coil pack assembly: Not started.
    • Ground insulation study: Not started.

 

  • Mechanical Structure:
    • Updated according to what Jose gave, 3D model has been updated.
    • New bladder geometry:  The detailed designed for the incapsulated structure around the bladder is in progress. Action: Purchase the tubes.
    • New thickness of Keys needs to be confirmed with Jose.
    • Action: Order shell as soon as possible.