Speakers:
Katerina Chrysalidis(CERN), Laura Lambert(CERN), Sebastian Rothe(CERN)
Cable identification ongoing, already had many visits on-site with cable owners
If you know you have cables around this area and have not been contacted by myself (Laura), please get in touch with me!
Equipment protection during dismantling works:
The roof of the RILIS lab is very dirty and full of dust, we anticipate a lot of dust during the dismantling process
A cleaning will be coordinated prior to dismantling to try to minimise this
As well, equipment owners will be asked to protect their own equipment, we are aware a lot of this equipment is very sensitive, so I would highly recommend protecting it with some plastic covering to protect from dust
The planned dismantling for the green cage and light structure is for ~3 weeks sometime in May or June
The planned dismantling for the I-beams starts in Sept
With the above in mind, I would like to ask people to please get in touch with myself, if people plan to perform any work on any of the equipment that is below or near the RILIS structure, so that we can coordinate well the works
Two detectors PAXIS301 (below RILIS) and 303 (inside RILIS) have been dismantled in anticipation of upgrade from RAMSES to CROME
14:40
→
14:45
Experiments related activities in the hall5m
Speakers:
Erwin Siesling(CERN), Hanne Heylen(CERN), Oscar Fjeld(CERN)
Upcoming
Wisard measurement campaign: Monday 26/1 - 8/2
Handling for transport of dewars
Send reminder to isolde community to inform us
COmmunication?
Cleaning campaign in next two weeks (announce)
Blue, red bins ordered already by Kati
Bins for Cupper cables
RP vacuum cleaner for general use available
Goals:
Make the hall presentable again/tidy up (visits, safety, ...)
Remove all unnecessary items from hall to free up space to move equipment related to ongoing projects
Make room in racks in the SAS
Contact owner of items --> how to proceed
Vacuum cleaners to make room in the SAS
Items in corridor next to ISOLDE
Big equipment plans
Gandalph - move out ISOLDE before end of February
Edingburgh chamber in HIE-ISOLDE - team is coming here in February to dismantle
Miniball clovers - move out before end of January
IDS boxes in SAS - stuck in administrative loop with customs
MIRACLS at LA2: before the end of January
508
For multipac: power cut on 9 February
Concrete slab for chiller
Installation of small eco-point
Cleaning
Deep clean
Weekly cleaning:
Nous allons mettre la feuille de traçabilité aujoud'hui dans les sanitaires A partir de cette semaine le planning sera le suivant Réfectoire les Mercredi et Vendredi Nettoyage hebdomadaire le Vendredi matin Bien cordialement
14:45
→
14:50
Activities in the primary areas - Coactivity management5m
Speaker:
Joachim Vollaire(CERN)
14:50
→
14:55
Activities in the expeirmental hall - Coactivity management5m
Speakers:
Erwin Siesling(CERN), Hanne Heylen(CERN), Oscar Fjeld(CERN)