Roland Garoby
(CERN)
3/7/12, 2:00 PM
Beam characteristics for HL-LHC [protons and ions (as far as possible)]
Time evolution (baseline plan): between LS1 and LS2, after LS2
Impact on other users.
Alessandra Lombardi
(CERN)
3/7/12, 2:30 PM
Update on Linac4 status and planning up to beam commissioning
Scenarios of connection: baseline plan, alternative scenarios (emergency replacement of Linac2 or Connection to PSB delayed to LS2, Benefits/drawbacks of having LS1.5)
Dr
Klaus Hanke
(CERN)
3/7/12, 3:00 PM
List of actions and planning of implementation (H- Injection, 2.0 GeV extraction…)
Studies
Impact on other users
PSB performance for LHC and other users in the different scenarios
Potential risks
Dr
Simone Gilardoni
(CERN)
3/7/12, 4:00 PM
List of actions and planning of implementation
Studies
Impact on other users
PS performance for LHC and other users in the different scenarios
Potential risks
Dr
Brennan Goddard
(CERN)
3/7/12, 4:30 PM
List of actions and planning of implementation
Studies
Impact on other users
SPS performance for LHC and other users in the different scenarios
Potential risks
Django Manglunki
(CERN)
3/7/12, 5:00 PM
List of actions and planning of implementation
Studies
Impact on other users
Performance for LHC and other users in the different scenarios
Potential risks
Massimo Giovannozzi
3/8/12, 9:00 AM
Status and outlook for 2012
What can (needs to) be done before LS1
Impact of studies and commissioning on classical CT or other hardware
Gabriel Metral
(CERN)
3/8/12, 10:00 AM
Can a super cycle be optimized with respect to losses ?
Ways to optimize losses/flux
Django Manglunki
(CERN)
3/8/12, 11:30 AM
Future beams for LHC
FT beams: primary beam interlock status, de-bunching, etc.
Radiation hazard with new ion species (all machines)
Rende Steerenberg
(CERN)
3/8/12, 12:00 PM
Impact of LHC beams on global loss budget in PSB, PS and SPS
Impact of LHC filling on other programs (ISOLDE, n-TOF, EA, NA, CNGS)
Stability of booster rings
Splitting (stability)
Sebastien Evrard
(CERN)
3/8/12, 2:30 PM
- Planned works for TAX repair
- Other activities in the caverns: targets, splitters, infrastructure improvements
- Where do we stand in terms of operations for 2012? Critical items?
- List of activities for LS1 in view of operation in 2014
Mr
Stephan Maury
(CERN)
3/8/12, 3:00 PM
- ELENA project status and plans
- Consolidation project for AD (machine) and hall. What is done in 2011 and plans/activities for 2012.
- Status of the AD target consolidation
Dr
Brennan Goddard
(CERN)
3/8/12, 4:00 PM
- Plasma Wakefield acceleration: new beam line and experimental area in TT61/West Area
- Neutrino facilities under study in LAGUNA-LBNO
- New short-baseline neutrino beam in PS or SPS
- Status and plans, impact to existing machines and experimental areas
Enrico Chiaveri
(CEA - Centre d'Etudes de Saclay (FR))
3/8/12, 4:30 PM
- Design of new area
- Timeline of activities
Richard Catherall
(CERN)
3/8/12, 5:00 PM
- Status and plans for 2012 experiments
- HIE-ISOLDE status and plans
- Foreseen activities for LS1
David Mcfarlane
(CERN)
3/9/12, 9:00 AM
Booster, PS, AD, SPS
Planning must take into account that in some cases the same teams will be working on the LHC as well as the SPS.
Dr
Vinod Chohan
(CERN)
3/9/12, 9:40 AM
LINAC3? CTF3? LINAC4 commissioning? (check on ISOLDE stable beam run??)
What services must be available and when in order for them to run?
Eva Sanchez-Corral Mena
(CERN)
3/9/12, 10:00 AM
Planning for the project and how access will be handled while the work is being done
Dr
Erk Jensen
(CERN)
3/9/12, 11:00 AM
PS and SPS Complex: What is to be done?, Why do we need to do it?, What are the requirements from other groups and priorities for:
i) Maintenance work
ii) Consolidation
iii) Upgrade related work
Jeremie Bauche
(CERN)
3/9/12, 11:30 AM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
i) Maintenance activities
ii) Replacing week/faulty SPS magnets
iii) Installing magnets with coated vacuum chambers in the SPS
Laurent Ducimetiere
(CERN)
3/9/12, 12:00 PM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
i) Maintenance work
ii) Consolidation
iii) Upgrade related work
Jose Antonio Ferreira Somoza
(CERN)
3/9/12, 2:00 PM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
I) Maintenance work
II) Consolidation
III) Upgrade related work
IV) List of activities generated by other groups
Dominique Missiaen
(CERN)
3/9/12, 2:30 PM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
I) Maintenance work
II) Consolidation
III) Upgrade related work
IV) List of activities generated by other groups
Gilles Le Godec
(CERN),
Karsten Kahle
(CERN)
3/9/12, 3:00 PM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
I) Maintenance work
II) Consolidation
III) Upgrade related work
Michele Battistin
(CERN)
3/9/12, 4:00 PM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
i) Maintenance work
ii) Consolidation
iii) Upgrade related work
iv) List of activities generated by other groups
Francois Duval
(CERN)
3/9/12, 4:30 PM
What is to be done? Why do we need to do it? What are the requirements from other groups and priorities for:
i) Maintenance work
ii) Consolidation
iii) Upgrade related work
iv) List of activities generated by other groups