RILIS coordination meeting 10

Europe/Zurich
CERN

CERN

    • 09:00 09:04
      SCE and HE 4m

      Week 21:

      • Dismantling of platform

      Week 22:

      • Dismantling of platform finalised - end of dismantling works!
      • Perform laser measurements for pre-fabricated I-beams - end of week 22
      Speakers: Severin D'Armancourt (CERN), Tiago Nico (CERN), Yann Denis Robert Seraphin (CERN)
      • Severin has followed up with contractor that all chemical waste to be separated properly
      • monobloc ready to be removed either tues or wed
    • 09:04 09:06
      AA and HE 2m

      Week 21:

      • Removal of monobloc - Tues 19th (EDH 11769159)
      Speakers: Didier Chapuis (CERN), Wiktor Stopa (EN-AA-AC), Yann Denis Robert Seraphin (CERN)
    • 09:06 09:08
      Scaffolding 2m

      Week 21:

      • Modifications of scaffolding to make area above beamline walk-able - end of week 21 (tbc)
      Speakers: Joris Maria (CERN), Michael Francois Bourbon
    • 09:08 09:12
      Integration 4m

      Week 21:

      • Finalise integration of cables now visible with light structure removed
      • Integrate neutron shielding blocks into new lab space based off of new table layout
      Speaker: Vincent Barozier
      • cable tray on the left cannot be moved as far as requested, might however be an option to move it less distance to the right
      • photo of laser table for laser launch
    • 09:12 09:15
      STI 3m

      Week 21/22

      • Removal of hard yellow tubing
      • Cleaning of I-beams laser dye contamination
      Speaker: Laura Lambert (CERN)