ISOLDE Technical Coordination Meeting (LS3)

Europe/Zurich
508/1-001 (CERN)

508/1-001

CERN

20
Show room on map
Zoom Meeting ID
62093336977
Host
Joachim Vollaire
Useful links
Join via phone
Zoom URL
    • 14:00 14:05
      General news - Review of minutes 5m
      Speakers: Erwin Siesling (CERN), Hanne Heylen (CERN), Joachim Vollaire (CERN)
    • 14:05 14:15
      Safety matters 10m
      Speakers: Hanne Heylen (CERN), James Devine (CERN), Joachim Vollaire (CERN)
    • 14:15 14:20
      IBDRS, Ventilation primary areas upgrade, BTY line @ 2 GeV 5m
      • False floor re-enforcement in B. 197: SCE has proposed the layout of the modified structure. Waiting for SY-EPC to launch the work (dismantling of existing racks and power converters for the BTY line)
      • IBDRS: GPS dump dismantling
      Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN), Melania Averna (CERN)
    • 14:20 14:25
      RILIS Laboratory upgrade project - activities update 5m
      Speakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
    • 14:45 14:50
      Mechanical Workshop and other support requests 5m
      Speaker: Oscar Fjeld (CERN)

      Last Week:

      • VITO machining:
        • Teflon and steel pushing mechanism for RF-Line tool
        • Stopper elements in Alu
        • 2 flanges with feedthrough openings
      • Miniball - moving of rack 
      • IDS - Lead usage in sample holder
      • Delivered design of ISOLDE sign for 197 smaller version

       

      Next week/New jobs:

      • VITO - profiles to be cut
      • LaBr detector cover design - Lorenzo
      • IDS - Ti44 sample opening at Medicis to take measures.
      • Design shielding Ti44 sample holder
    • 14:50 14:55
      Planned visits and AOBs 5m

      From Hanne:
      • AC cut for laser labs in 508
      o VITO: needs to commission the rf-laser spectroscopy setup, which is a development committed in an ERC Grant ending August 2027 so they need a temperature controlled lab for a longer period after August. We had a discussion with Alexandre last week and the preliminary idea is that a mobile unit could be installed and the ducts could then go through the false ceiling via 508/R-008 to the outside. This will of course be a costly affair, even for the rent of the unit alone (who will pay?). Once it is clear what requirements VITO has in terms of T and stability, EN/CV will look into renting/buying a mobile unit. Still needs more detailed discussion.
      o COLLAPS would only want to be sure to be able to continue measuring until end of August. They asked if they could put their own mobile unit for ~1 week, with either the doors open (to be discussed with EP safety) or by putting the exhaust through an existing hole (?) into the ISOLDE hall. To be discussed, it would be only for a short period at the end of August.
      o CRIS, no input so far, sent reminder.
      • Temporary access ramp 508 was reinforced after the storm on Wednesday
      • Can we plan the installation of coat hangers for helmets by Oscar?
      • Visits
      o ISOLTRAP start scaffolding installation next week Thursday 18/6 -> any impact on visits during that period, first one after 18/6 is on the 25th?.

      Speaker: Hanne Heylen (CERN)